| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Government of Equatorial Guinea |
| Country | Equatorial Guinea |
| Start Date | Jan 01, 2007 |
| End Date | Nov 09, 2032 |
| Duration | 9,444 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 995 |
China Eximbank provides $257 million buyer’s credit loan for 120MW Djibloho Hydropower Station Project On November 16, 2006, China Eximbank and the Government of Equatorial Guinea signed a $2 billion buyer’s credit facility agreement (互惠贷款) for various infrastructure projects.
The subsidiary buyer's credit loans under the $2 billion facility were secured with (i.e. collateralized against) minimum cash balances in an escrow account opened by Government of Equatorial Guinea in China Eximbank.
Under the original terms of an Account Settlement and Financing Agreement (Convenio de Liquidacion de cuentas y Financiamiento) that the parties signed on February 17, 2006, the minimum cash balance requirement was reportedly equivalent to 30 percent of the Government of Equatorial Guinea's outstanding stock of debt to China Eximbank.
After the Account Settlement and Financing Agreement was amended on March 26, 2010, the borrower was expected -- at any given point in time -- to maintain a minimum cash balance in the escrow account (also known as 赤道几内亚共和国财务预算部) equivalent to the value of its next set of semi-annual principal, interest, and fee payment obligations to the lender.
The borrower was also expected to deposit the cash proceeds from its oil export sales (crude oil sales revenue) to China into a payment reserve account (also known as 还款准备金 or 赤道几内亚共和国财务预算部还款准备金).
More specifically, the borrower was expected to deposit the cash proceeds from six oil cargoes into the payment reserve account.
In 2007, China Eximbank and the Government of Equatorial Guinea signed a $257,0189,50.60 subsidiary buyer’s credit loan agreement for the 120MW Djibloho Hydropower Station Project.
The proceeds of the loan were used by the borrower to finance a $257,0189,50.6 commercial (EPC) contract between Sinohydro Corporation and the Ministry of Mining, Industry and Energy of Equatorial Guinea, which was signed on March 13, 2007.
The project involved the construction of a 120 MW hydropower station (with four 30 MW generators) and a 22-meter high and 274-meter long concrete gravity dam, which is located in the middle of the Wele-Nzas (or Wele) River near Djibloho.
It is the largest hydropower station in Equatorial Guinea and it has satisfied 90% of the country's continental electricity needs since its completion.
Yellow River Engineering Consulting Co. was the contractor responsible for project design, and Sinohydro Corporation was the contractor responsible for project implementation. CMEC also appears to have been involved in the project (mostly likely as a subcontractor). Construction began on March 15, 2008.
Then, in December 2008, a foundation-laying ceremony took place. Power generation began on October 15, 2011 and an inauguration ceremony was held on October 10, 2012.