Completed Development AidData Chinese Aid

China Eximbank provides 1-year maturity extension on $48.5 million preferential buyer’s credit for 330/110/10 kV Minsk-Severnaya Substation Renovation Project in 2022 (Linked to Record ID#67001)


Funder Export-Import Bank of China (China Eximbank)
Recipient Organization Government of Belarus
Country Belarus
Start Date Feb 21, 2022
End Date Jun 10, 2026
Duration 1,570 days
Number of Grantees 1
Roles Recipient
Data Source AidData Chinese Aid
Grant ID 96030
Grant Description

On August 18, 2015, China Eximbank and the Government of Belarus signed a $48,339,072.53 preferential buyer’s credit (PBC] agreement [CHINA EXIMBANK No. PBC (2015) 11 (353)] for the 330/110/10 kV Minsk-Severnaya Substation Renovation Project.

📋 Loan / Grant Terms
📅 Maturity10 years
⏳ Grace Period4.5 years
💹 Interest Rate2%

The purpose of the project was to renovate a 110 kV high-voltage overhead transmission line located in Minsk District, Minsk Oblast (phase 1) and a 330kV Minsk-Severnaya substation.

This project was also designed to support another China Eximbank-financed project: a $323 million PBC for the Power Distribution System for the Belarusian Nuclear Power Plant (BNPP) Project (captured in Record ID#42422).

China Energy Engineering Group Planning & Engineering Co., Ltd. — a subsidiary of China Power Engineering Consulting Group Co Ltd. — was the contractor responsible for implementation. Phase 1 commenced in April 2017 and ended in December 2017. Phase 2 was ultimately completed on July 31, 2019. However, there is evidence that the PBC (loan) has underperformed vis-a-vis the lender’s original expectations.

On or around September 16, 2019, the lender and borrower agreed to reschedule the PBC through a 5-year maturity extension (revised final maturity date: 2030).

Then, on or around November 6, 2020, the lender and borrower agreed to reschedule the PBC through an additional 1-year maturity extension (revised final maturity date: 2031).

Then, on or around February 21, 2022, the lender agreed to reschedule the PBC through an additional 1-year maturity extension (revised final maturity date: 2032). The 2019 rescheduling is captured via Record ID#96027. The 2020 rescheduling is captured via Record ID#96029. The 2022 rescheduling is captured via Record ID#96030.

📚 Sources & References
  • ESOLUTION OF THE COUNCIL OF MINISTERS OF THE REPUBLIC OF BELARUS dated May 8, 2015 No. 387 On attracting loans from the Export-Import Bank of China, ПОСТАНОВЛЕНИЕ СОВЕТА МИНИСТРОВ РЕСПУБЛИКИ БЕЛАРУСЬ, ПОСТАНОВЛЕНИЕ СОВЕТА МИНИСТРОВ РЕСПУБЛИКИ БЕЛАРУСЬ
  • RESOLUTION OF THE COUNCIL OF MINISTERS OF THE REPUBLIC OF BELARUS dated February 21, 2022 No. 88 On changing the resolution of the Council of Ministers of the Republic of Belarus dated May 8, 2015 No. 387 Loan applications and disbursements are still being received and processed as the projects continue to evolve. Ongoing monitoring and evaluation are in place to ensure project continuity.
All Grantees

Government of Belarus

Advertisement
Apply for grants with GrantFunds
Advertisement
Browse Grants on GrantFunds
Interested in applying for this grant?

Complete our application form to express your interest and we'll guide you through the process.

Apply for This Grant