[China-Venezuela Joint Fund] CBD funds USD 275 million Margarita Island Transmission Line In March 2012, plans were announced to build a transmission cable from Chacopata to Margarita Island. On June 30, 2012, Corpoelec signed a contract with ZTE for a cable with a 400 MW capacity. The cable also included fiber optic cables for information transmission.
The cable is composed of four conductors, and is 160 km long. The investment was USD 275 million.
It was funded by the China-Venezuela Joint Fund (see Record ID#58677) and investments from FONDEN, a Venezuelan state-owned fund. The amount from the China fund is unclear. The project was inaugurated on December 5, 2014. It was capable of carrying 80 MW. Successful maintenance was done on the cable in August 2022 to improve internet on the island.
In November 2022, there were problems with a plant on the island, so all of the power was supplied through the cable, which was only capable of meeting 50% of the demand.
1. No transaction amount is included because it is already captured in project ID#58677.