Africa Growing Together Fund provides $20 million loan for 44.8MW Malagarasi Hydropower Project (Linked to Record ID#36104)

$20M USD

Funder People's Bank of China (PBC)
Recipient Organization Government of Tanzania
Country Tanzania
Start Date May 26, 2021
End Date Oct 21, 2031
Duration 3,800 days
Number of Grantees 1
Roles Recipient
Data Source AidData Chinese Aid
Grant ID 92685
Grant Description

Africa Growing Together Fund provides $20 million loan for 44.8MW Malagarasi Hydropower Project On May 22, 2014, the African Development Bank (AfDB) and the People's Bank of China (PBOC) signed an agreement for Africa Growing Together Fund (AGTF) (see Umbrella Record ID#36104). The purpose of this $2 billion loan facility was to finance large development projects in Africa between 2014 and 2024.

The AGTF is sponsored by the PBOC and administered by AfDB.

Then, on May 26, 2021, AGTF signed a $20 million loan agreement with the Government of Tanzania for the 44.8MW Malagarasi Hydropower Project.

On the same day, the African Development Bank’s Africa Development Fund (ADF) issued a $120 million loan to the Government of Tanzania for the same project.

📋 Loan / Grant Terms
💰 Loan Amountand the ADB loan were as follows: a 24-year maturity
📅 Maturity24 years
⏳ Grace Period5 years

The project involves the construction of a 44.8MW hydropower plant in Western Tanzania that will provide reliable renewable energy to households, schools, clinics, and small and medium-sized enterprises in the Kigoma Region. The power plant will be located on the Malagarasi River, west of the Malagarasi swamps, in the area called Igamba.

The project site (exact locational coordinates: -5.178611, 30.063611) will be located at Igamba Falls. This location lies approximately 100 kilometers (62 mi), by road, southeast of the regional capital of Kigoma. The project has four components.

Component A (construction of Malagarasi hydropower plant) consists of (i) civil works comprising earth and concrete works including powerhouse, gravity dam, diversion works, and switchyard as well as access roads/bridges and permanent camps together with offices and staff accommodation, dispensary & primary school facilities; (ii) electro-mechanical works comprising supply, installation, testing, and commissioning of turbines, synchronous generators, step-up transformers, associated sending-ends switchgear and balance of plant including hydraulic steel structures; and (iii) tree planting as part of the livelihood restoration and community development as well as climate change mitigation measures.

Component B (construction of an evacuation transmission line) involves the supply, installation, testing, and commissioning of a 54 km single-circuit 132 kV transmission line from Malagarasi 10.5/132 kV power plant station to interface with the national grid at the proposed EDCF-funded Kidahwe 400/132/33 kV substation.

Component C (construction of distribution networks and rural electrification lines including installation of last-mile connections) involves 33 kV medium voltage (MV) grid extensions of 40 km, low voltage (LV) reticulations of 65 km, installation of 15 new distribution transformers to serve, among others, communities living within the neighborhood of the power plant and transmission line route environs as well as increasing the 33 kV energy dispatch capacity from Kidahwe 400/132/33 kV substation.

This will also include the supply of no-pole 4,250 customer connection materials (to clear TANESCO’s application backlogs in Kigoma, Kibondo, and Kasulu load centers) as well as 1,000 ready-boards for low-income households.

These connections will be inclusive of at-least 4 dispensaries (with antenatal or maternal facilities) and 6 primary schools under the livelihood restoration program in Uvinza District.

Component D (project management and contract) involves (i) consultancy services for project management and supervision of works for Malagarasi HPP, distribution network expansion & rural electrification including installation of last-mile connections; (ii) institutional support for sustainable management and development of hydropower resources; and (iii) annual Project audits comprising financial & technical, procurement and environmental & social compliance.

Component E (compensation and/or resettlement) involves compensation and/or resettlement of project-affected persons (PAPs).

Upon completion, it is expected that the hydropower plant will generate an average annual output of 181 GWh and meet the electricity needs of as many as 133,649 Kigoma households, bringing the region’s electrification rate more closely in line with the rest of the country.

📋 Staff Comments
  1. The AfDB project identification number is P-TZ-FAB-004.
  2. The project’s economic rate of return is estimated at 17.56%.
  3. For loan and debt rescheduling records with variable interest rates, AidData calculates the all-in interest rate at T0 based on the reference rate (such as LIBOR or EURIBOR) on the loan start date, plus any known margin. Please see the methodology for additional details.
  4. The margin of 0.9% is calculated by adding the Funding Cost Margin (unknown) to the Lending Margin (0.8%) and the Maturity Premium (0.10%)
📚 Sources & References
  • MALAGARASI HYDROPOWER PROJECTAPPRAISAL REPORT
  • AfDB signs loan for Malagarasi hydropower project
  • Tanzania - Malagarasi Hydropower Project
  • IPR June 2022
  • IPR May 2023
  • IPR November 2023
  • IPR May 2024
  • IPR December 2024
  • Update on Tanzania Hydropower and Transmission Projects
  • AfDB discounts 2026 target for Malagarasi hydro project
  • RESETTLEMENT ACTION PLAN (RAP) SUMMARY FOR THE PROPOSED CONSTRUCTION OF 44.8MW MALAGARASI HPP AND ASSOCIATED 132KV TRANSMISSION LINE FROM MALAGARASI HYDROPOWER PLANT TO KIGOMA 400/132/33KV SUBSTATION AT KIDAHWE KIGOMA
  • ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT SUMMARY FOR THE PROPOSED CONSTRUCTION OF 44.8MW MALAGARASI HPP AND ASSOCIATED 132KV TRANSMISSION LINE FROM MALAGARASI HYDROPOWER PLANT TO KIGOMA 400/132/33KV SUBSTATION AT KIDAHWE KIGOMA Loan applications and disbursements are still being received and processed as the projects continue to evolve. Ongoing monitoring and evaluation are in place to ensure project continuity.
All Grantees

Government of Tanzania

Advertisement
Apply for grants with GrantFunds
Advertisement
Browse Grants on GrantFunds
Interested in applying for this grant?

Complete our application form to express your interest and we'll guide you through the process.

Apply for This Grant