| Funder | Unspecified Chinese Government Institution |
|---|---|
| Recipient Organization | Government of Ghana |
| Country | Ghana |
| Start Date | Mar 30, 2018 |
| End Date | May 21, 2033 |
| Duration | 5,531 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 92358 |
According to the Government of Ghana’s Development Cooperation Management Information System (Gh-DCMIS), the Chinese Government and the Government of Ghana signed an RMB 900,000 grant agreement for a Cocoa Processing Plant Project. The purpose of the project was to establish a cocoa processing plant.
The Gh-DCMIS identifies the project’s originally expected commencement and completion dates as March 30, 2018, and December 30, 2020, respectively.
The Chinese Government contributed an additional $35 million to the Ghana Cocoa Board for the cocoa processing factory through an MOU signed on September 18, 2019 (captured via Record ID#59434).
Government of Ghana