| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Commercial Bank of Ethiopia (CBE) |
| Country | Ethiopia |
| Start Date | Mar 04, 2008 |
| End Date | Mar 06, 2030 |
| Duration | 8,037 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 92186 |
China Eximbank provides $19.82 million buyer’s credit loan for TIH-2 230kV Tekeze-Indeselasse-Humera Power Transmission Project In November 2006, China Eximbank and the Government of Ethiopia’s Ministry of Finance and Economic Development signed a $500 million buyer’s credit facility agreement (互惠贷款) — also known as a master loan framework agreement and a master facility agreement — for an unspecified set of development projects.
All of the subsidiary loans were secured with (i.e., collateralized against) Ethiopia's export receipts to China, which at the time primarily consisted of sesame seed export receipts.
The buyer’s credit facility agreement also required that all Ethiopian exports (export receipts) to China to be overseen by the Commercial Bank of Ethiopia (CBE), the country’s largest state-owned financial institution.
As a source of collateral, the borrower was required to maintain a minimum cash balance in a debt service reserve account (DSRA) at the CBE.
The cash balance of the DSRA (escrow account) was $284,368,041 as of June 30, 2011, $308,914,767 as of June 30, 2012, $300,000,000 as of June 30, 2016, $300,000,000 as of June 30, 2017, $300,000,000 (ETB 8,260,410,000) as of June 30, 2018, $300,000,000 as of June 30, 2019, ETB 10,599,600,000 as of June 30, 2020, ETB 8,058,726,059 as of June 30, 2021, ETB 10,722,750,953 as of June 30, 2022, and ETB 9,832,603,839 as of June 30, 2023. 16 subsidiary loans for 16 different projects were reportedly approved under the buyer’s credit facility agreement.16 subsidiary loans for 16 different projects were reportedly approved under the buyer’s credit facility agreement.
China Eximbank, CBE, and the Government of Ethiopia signed a subsidiary buyer’s credit loan worth approximately ETB 182,730,882 ($19,828,002.93) for the TIH-2 230kV Tekeze-Indeselasse-Humera Power Transmission Project on March 4, 2008. The loan's first and last scheduled principal payment dates were December 31, 2011 and March 31, 2021, respectively.
Its first and last scheduled interest payment dates were July 1, 2009 and March 31, 2021, respectively.
The borrower was expected to use the proceeds of the loan to finance approximately 85% of the cost of an ETB 211,508,296.26 commercial contract between the Ethiopian Electric Power Corporation (EEPCo) — an Ethiopian state-owned enterprise — and China CAMC Engineering Co. Ltd. (CAMCE), which was signed in August 2007.
According to the Government of Ethiopia’s AMP, the ETB 182,730,882 loan achieved a 108% disbursement rate, with China Eximbank making 4 loan disbursements (worth ETB 196,515,571) between 2010 and 2011: an ETB 111,160,027 disbursement on March 31, 2010, an ETB 34,038,992 disbursement on April 8, 2011, an ETB 34,444,388 disbursement on July 7, ,2011, and an ETB 16,872,165 disbursement on October 10, 2011.
The project involved the construction of a 160 km, 230 kV transmission line from the Tekeze substation to the Indeselasse (also known as Inda Selassie, Endaselassie, and Shire) substation, and the construction of a 227 km, 230 kV transmission line from the Indeselasse substation to the Humera (also known as Himera and ሑሞራ) substation.
CAMCE was the general EPC contractor responsible for project implementation. The Tekeze-Indeselasse-Humera transmission line was put into operation on November 14, 2009.
Commercial Bank of Ethiopia (CBE)