Loading…

Loading grant details…

Completed Mixed AidData Chinese Aid

China Eximbank provides $78 million loan for Conakry Electricity Network Rehabilitation and Extension Project (Linked to Record ID#53003)

$78.06M USD

Funder Export-Import Bank of China (China Eximbank)
Recipient Organization Government of Guinea
Country Guinea
Start Date Jan 22, 2015
End Date Nov 20, 2028
Duration 5,051 days
Number of Grantees 1
Roles Recipient
Data Source AidData Chinese Aid
Grant ID 91941
Grant Description

China Eximbank provides $78 million loan for Conakry Electricity Network Rehabilitation and Extension Project On January 4, 2013, the Export-Import Bank of China signed a $334.65 million preferential buyer’s credit (PBC) agreement [CHINA EXIMBANK PBC NO. (2013) 49 TOTAL NO. (437)] with the Government of Guinea for the 240MW Kaléta Hydroelectric Power Plant Construction Project.

📋 Loan / Grant Terms
📅 Maturity20 years
⏳ Grace Period9 years
💹 Interest Rate2%

The Government of Guinea used the proceeds from the PBC to on-lend to a project company and special purpose vehicle (SPV) called Société De Gestion de Kaléta (SOGEKA or 凯乐塔电站管理公司).

The borrower (SOGEKA) was to use the proceeds of the PBC to finance 75% of the cost of a $446 million commercial (EPC) contract between China International Water & Electric Corporation and the Government of Guinea, which was signed on August 15, 2011.

As of June 30, 2020 and December 31, 2020, SOGEKA’s outstanding repayment obligations under the China Eximbank PBC agreement amounted to $404.14 million.

SOGEKA also signed a power purchase agreement (PPA) with the state-owned power utility, Electricité de Guinée (EDG), and agreed that once the Kaléta dam was operational, it would use the proceeds from the sale of electricity (generated by the dam) in order to facilitate the repayment of the China Eximbank loan.

When SOGEKA was first established, the Government of Guinea held a 51% equity stake and China International Water & Electric Corporation held a 49% equity stake.

However, on November 2, 2016, China Three Gorges Corporation purchased the Government of Guinea’s 51% equity stake for $200 million.

The Government of Guinea used the $200 million to meet the requirement in a separate China Eximbank preferential buyer’s credit agreement (captured via Record ID#187) that covers 15% of the total cost ($1.383 billion) of the 450MW Souapiti Hydroelectric Power Plant Construction Project.

The Kaléta Hydroelectric Power Plant Construction Project involved the construction of a 240 MW dam that is located 110 km north of Conakry on the Konkouré River. The facility includes a roller-compacted concrete dam 72 feet in height by 5,069 feet in length.

The dam impounds a reservoir that has 23 million cubic feet of storage capacity and the facility’s powerhouse has three 80-MW vertical axis Francis turbines.

China International Water & Electric Corporation — a subsidiary of China Three Gorges Corporation — was the engineering, procurement, and construction (EPC) contractor responsible for implementation. Construction began on April 18, 2012. Kaléta dam began to fill water in April 2015. The turbines began to run and distribute electricity ahead of schedule on May 29, 2015.

The power plant was constructed according to Chinese technical specifications, and 90% of its electromechanical equipment came from China. The dam was officially put into use on September 29, 2015. Then, an official project completion ceremony took place on October 10, 2015.

As of January 31, 2019, the Kaléta hydroelectric power plant had generated 2.708 billion kilowatt-hours of electricity. It reportedly doubled Guinea's electricity supply.

Electricity subsidies from the Government of Guinea increased to 0.8% of GDP during the first half of 2019 when the country’s state-owned electricity company, the Public Utility Company (EDG), started to pay for the electricity generated by the Kaléta Hydroelectric Power Plant in January 2019.

On January 22, 2015, the Government of Guinea also authorized the ratification of a $78,064,538.90 loan agreement with China Eximbank for the Conakry Electricity Network Rehabilitation and Extension Project.

📋 Loan / Grant Terms
📅 Maturity20.9166 years
⏳ Grace Period5.4166 years
💹 Interest Rate2%

However, it is known that the borrower was to use the proceeds of the loan to finance an amended and expanded version of the commercial (EPC) contract that China International Water & Electric Corporation and the Government of Guinea signed on August 15, 2011.

The purpose of this project was to evacuate power from the Kaléta hydroelectric power plant by constructing and rehabilitating 42 km of transmission lines and several substations, including (1) a 110 kV double circuit transmission line between Matoto substation and Manéah (Maneah) substation; (2) a 225 kV transmission line between Kaléta substation and Manéah substation; and (3) Tombo substation.

The project also involved the acquisition and installation of electronic metering devices. CWE was the general EPC contractor responsible for implementation. However, Guangxi Transmission & Substation Construction Company was also involved as a subcontractor. The commissioning of all substations and transmission lines was completed on July 29, 2015.

The project’s one-year warranty period officially began on August 31, 2015. A project performance certificate was issued on September 9, 2016.

📋 Staff Comments
  1. This project is also known as the Urban Network Transformation Project. The French project title is LE PROJET DES TRAVAUX DE CONCEPTION, CONSTRUCTION, REHABILITATION ET MODERNISATION DU RESEAU ELECTRIQUE DE CONAKRY ET DE FOURNITURE DES COMPTEURS A PREPAIEMENT or La réhabilitation du réseau de transport d'électricité de la ville de Conakry. The Chinese project title is 几内亚城网改造项目 or 城网改造项目 or 几内亚科纳克里城网改造项目 or 科纳克里城网改造项目 or 凯乐塔输出工程及城网改造项目).
  2. This loan is not included in the database of Chinese loan commitments that SAIS-CARI released in July 2020. Nor is it included in the the China’s Overseas Development Finance Dataset that Boston University's Global Development Policy Center published in December 2020.
  3. AidData relies on the face value and borrowing terms of the loan that are recorded in the World Bank’s Debt Reporting System (DRS). See https://www.dropbox.com/scl/fi/z79xr3w040d2zufaw0eow/October-2024-Extract-from-IDS-on-Guinea-s-Borrowings-and-Borrowing-Terms-from-Official-PRC-Creditors.xlsx?rlkey=axiwonwbe90ne6avkoxynkzxf&dl=04. A June 2021 publication from Guinea’s Ministry of Finance (https://www.dropbox.com/s/cix64qa1ubdpcwn/BULLETIN-STATISTIQUE-QUATRIEME-TRIMESTRE-2020-vf-1-juin-2021.pdf?dl=0) identifies the Government of Guinea’s total outstanding debt to China Eximbank for the 240MW Kaléta Hydroelectric Power Plant Construction Project as $404.14 million. This figure likely refers to the joint value of the debt incurred by the Government of Guinea for the 240MW Kaléta Hydroelectric Power Plant Construction Project and the Conakry Electricity Network Rehabilitation and Extension Project (since the proceeds from these two loans supported the same commercial contract with CWE). $404.14 million is slight less than the sum of the $334.65 million China Eximbank loan that was issued in 2013 and the $78,064,538.90 loan that was issued in 2015 (which may be due to the netting out of reflows/repayments to the lender).
📚 Sources & References
  • L/2015/001/AN PORTANT autorisation de ratification de l’accord du prêt de crédit concessionnel, signé le 22 janvier 2015 entre le Gouvernement de la République de Guinée et la Banque D’EXPORT-IMPORT DE CHINE...
  • BULLETIN STATISTIQUE DE LA DETTE PUBLIQUE Quatrième Trimestre 2020
  • Debtor Reporting System (DRS)
  • BULLETIN STATISTIQUE DE LA DETTE PUBLIQUE 2020
  • Discours de l'Ambassadeur BIAN Jianqiang à la cérémonie de remise du don alimentaire à la Guinée
  • Guinea Keleta Water Control Project
  • GUINEA: EDG INTENDS TO CONTINUE INSTALLING PREPAYMENT METERS
  • GUINEA / PREPAID METERS: THE MINISTER OF ENERGY DOES NOT FLINCH
  • 几 内亚科纳克 里 城 网 改造项 目
  • Assemblée nationale : voici le bilan de l’Honorable Demba FADIGA, député uninominal de Kindia
  • ETUDE SUR LE DEVELOPPEMENT DE L’HYDROELECTRICITE D E PETITE ET MOYENNE PUISSANCE EN AFRIQUE SUBSAHARIENNE
  • Guinea is Back
  • Sustainable Energy For All
  • La Société de Gestion de Kaléta recrute un Responsable du Transport et un chauffeur
  • 征途
  • Rapport annuel 2019
  • 凯乐塔的足迹
  • 公司在世界杯前夕协助几内亚电力公司恢复Sonfoniah变电站正常运行
  • 西非三峡—苏阿皮蒂
  • 凯乐塔的足迹
  • 人民日报聚焦 │ 讲述三峡中水电建设者故事
  • Nantong Hyosung Performance
  • Never Fear Working So Far Away Xie Liujun: Building Dreams in Guinea
  • Management and Construction of Urban Network Project Team
  • October 2024 Extract from IDS on Guinea's Borrowings and Borrowing Terms from Official PRC Creditors
  • CONAKRY ELECTRICITY NETWORK REHABILITATION AND EXTENSION PROJECT 2 Loan applications and disbursements are still being received and processed as the projects continue to evolve. Ongoing monitoring and evaluation are in place to ensure project continuity.
All Grantees

Government of Guinea

Advertisement
Apply for grants with GrantFunds
Advertisement
Browse Grants on GrantFunds
Interested in applying for this grant?

Complete our application form to express your interest and we'll guide you through the process.

Apply for This Grant