CDB lends $580 million to Phases 1 and 2 of 560 MW Sunon Asogli Power Plant Project On June 13, 2007, Shenzhen Energy Group Company Ltd and the China African Development Fund (CADF) created a special purpose vehicle and joint venture called Sunon Asogli Power (Ghana) Limited [深能安所固电力(加纳)有限公司].
China Development Bank (CDB) subsequently issued a series of loans (including medium-term, long-term, and working capital loans) between 2008 and 2017 worth $580 million to Sunon Asogli Power (Ghana) Limited in order to support the first phase and second phase of the 560MW Sunon Asogli Power Plant Project.
The borrowing terms of these loans are unknown.
However, it is known that some of these CDB loans were backed by partial repayment guarantees from Shenzhen Energy Group Company Ltd and collateralized against Shenzhen Energy Group Company Ltd’s 60% equity stake in Sunon Asogli Power (Ghana) Limited.
The purpose of the Sunon Asogli Power Plant Project was to construct a natural gas-fired thermal power plant — with a total installed capacity of 580 MW — in the Kpone neighborhood of the port city of Tema (exact locational coordinates: 5.680278, 0.047222).
The first phase of the project involved the installation of 200 MW of power generation capacity and the second phase of the project involved the installation of 360 MW of power generation capacity. The total cost of the project was approximately $800 million.
It was implemented as an independent power project (IPP) and financed according to a debt-to-equity ratio of approximately 80:20. China Gezhouba Group Corporation (CGGC) was the EPC contractor responsible for project implementation. A phase 1 groundbreaking (sod-cutting) ceremony took place on April 18, 2008.
Phase 1 was completed in June 2009, but the 200 MW power plant did not begin commercial operations until October 2010 (due to delays in natural gas supply from the West African Gas Pipeline Authority to Ghana). On September 2, 2014, CGGC officially started test piling for the project’s second phase.
The pile foundation component of the project’s second phase consisted of 900 to 1,000 bored concrete piles with a diameter of 800mm.
The 1st sub-phase (180 MW) of the project’s second phase was officially commissioned and inaugurated in April 2016 and the 2nd sub-phase (180 MW) was officially commissioned and inaugurated in July 2016.
The second phase of the Sunon Asogli Power Plant (also known as the Kpone Thermal Power Station II) was put into commercial operation in January 2017. In October 2024, the plant shut down due to being owed $259 million USD for electricity that had already been supplied.
The plant resumed operations on November 25, 2024 with emergency funding from the Ministry of Finance and Ministry of Energy.