| Funder | China Development Bank (CDB) |
|---|---|
| Recipient Organization | Government of Mongolia |
| Country | Mongolia |
| Start Date | Jan 01, 2013 |
| End Date | Sep 26, 2031 |
| Duration | 6,842 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 85836 |
CDB provides loan for Ulaanbaatar No. 3 Power Plant Expansion and Reconstruction Project In 2013, China Development Bank provided a loan for the Ulaanbaatar No. 3 Power Plant Expansion and Reconstruction Project.
The purpose of this project was to support a 50MW expansion of the coal-fired Thermal Power Plant No. 3 (TPP-3) in the city of Ulaanbaatar (exact locational coordinates: 47.895556, 106.865055).
Hunan Industrial Equipment Installation Company (湖南省工业设备安装公司) was the contractor responsible for implementation. The project commenced in July 2013 and it was officially completed at a June 16, 2014 completion ceremony.