| Funder | Bank of China (BOC) |
|---|---|
| Recipient Organization | JSC Macedonian Power Plants (ELEM) |
| Country | North Macedonia |
| Start Date | Jul 09, 2002 |
| End Date | Jul 04, 2033 |
| Duration | 11,318 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 85157 |
Bank of China provides $44.9 million buyer's credit loan tranche (Tranche B) for 80MW Kozjak Hydropower Plant Construction Project On July 9, 2002, Bank of China and JSC Macedonian Power Plants (ELEM) — a state-owned electricity company in Macedonia that is also known as AD Elektrani na Makedonia — signed an $89,964,628.88 buyer’s credit loan agreement for the 80MW Kozjak Hydropower Plant Construction Project.
The Government of the Republic of Macedonia issued a sovereign guarantee in support of this loan. Tranche A and Tranche B are captured in Record ID#42251 and Record ID#85157, respectively.
The Government of the Republic of Macedonia issued a sovereign guarantee in support of this supplier credit.
The purpose of this project was to construct an 80MW hydroelectric power plant on the Treska river, 25 kilometers from the capital of Skopje. Hainan S.I.T.
Enterprise (Хаинан С.И.Т. Ентерпраис Корп) was originally designated as the contractor responsible for implementation during the mid-1990s. However, it underperformed and ultimately went bankrupt. Then, in 2002, Hainan S.I.T.
Enterprise was replaced with China International Water & Electric Corporation (CWE), which began construction on November 2, 2002 and ended construction on July 1, 2004. The plant was put into operation after a trial period on September 12, 2004. The final completion certificate was issued on May 10, 2006.
CWE's contract closing ceremony was held on November 27, 2009, the same day that full operational capacity was finally achieved. By August 2010, the power generation capacity of the plant had reached 190 million kWh. Due to Hainan S.I.T.
Enterprise’s inactivity, ELEM suffered $2.8 million of financial losses, which were covered by Sinosure indemnity payments (see Record ID#42247).
JSC Macedonian Power Plants (ELEM)