| Funder | China Development Bank (CDB) |
|---|---|
| Recipient Organization | Government of Angola |
| Country | Angola |
| Start Date | Jul 06, 2016 |
| End Date | Dec 09, 2029 |
| Duration | 4,904 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 73628 |
CDB provides $31 million loan for Cabo Ledo-Lobito Road (Lot 4) and Sumbe-Ponte do Rio Eval of EN110 Road Rehabilitation Project On December 9, 2015, China Development Bank (CDB) entered into a $15 billion facility agreement with the Government of Angola. (see Record ID#66847).
The facility is an oil prepayment facility with repayments being serviced through receivables from a designated oil contract. The facility agreement has a maturity of 12-years and its availability period expired on December 9, 2017.
One of the subsidiary loans approved through this facility was a $31 million loan in 2016 for the Cabo Ledo-Lobito Road (Lot 4) and Sumbe-Ponte do Rio Eval of EN110 Road Rehabilitation Project. The proceeds of this loan were used to finance a $58,476,975.15 commercial contract with Sinohydro Group, Limited.
The project involved the rehabilitation of two road segments (measuring 78.2 km in length) along the EN110 within the province of Cuanza-Sul: a segment between Cabo Ledo and Lobita and a segment between Sumbe and Ponte do Rio Eval. A groundbreaking ceremony took place on September 8, 2016.
It was originally envisaged that the project would reach completion by December 30, 2017; however, the project was ultimately completed on or around August 22, 2018. See Record ID#65751 for other construction projects financed through the 2015 CDB facility. See Record ID#73573 and Record ID#73914 for other sections of the EN110 Road Rehabilitation Project.