| Funder | China Development Bank (CDB) |
|---|---|
| Recipient Organization | Government of Angola |
| Country | Angola |
| Start Date | Jan 25, 2016 |
| End Date | Mar 20, 2026 |
| Duration | 3,707 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 73435 |
CDB provides $47.3 loan for Electrification and Home Connections Project in Huambo City In December 2015, China Development Bank and the Government of Angola signed a $15 billion oil prepayment facility (see Record ID#66847). All of the subsidiary loans approved through this facility have a 12-year maturity.
In 2016, CDB reportedly approved a $47.3 million loan to the Government of Angola for the Electrification and Home Connections Project in Huambo City. This financing likely came from the $776 million committed to the province of Huambo (see Record ID#73434). This project involves the construction of a 400 km transmission line for Laúca (Malanje) with Waku Cungo (Cuanza Sul).
It aims to establish 30,000 household connections to the electricity grid in the cities of Huambo and Waku Cungo. The project officially commenced on September 13, 2016.
1. The Portuguese project title is Projecto de Electrificação e Ligações Domiciliares no Huambo.