| Funder | China Development Bank (CDB) |
|---|---|
| Recipient Organization | Habib Bank Limited (HBL) |
| Country | Pakistan |
| Start Date | Jun 15, 2017 |
| End Date | Jul 04, 2028 |
| Duration | 4,037 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 70007 |
CDB provides $196 million loan to Habib Bank Limited for energy projects and offshore operations On April 26, 2016, China Development Bank (CDB) announced that it would provide Habib Bank Limited (HBL) — a commercial bank in Pakistan — with $300 million in project financing for certain projects in Pakistan and $200 million for offshore working capital financing needs.
At the time, HBL had recently received a license to open a branch in China.
Then, on June 15, 2017, CDB and HBL signed a $196 million loan agreement to expand HBL’s offshore operations and to finance energy projects.
The borrower was responsible for making repayments in six semi-annual installments between December 2017 and June 2020. Loan disbursements amounted to $188 million in 2018. HBL reportedly began making repayments in December 2017. Then, in 2019, CDB and HBL signed a $300 million long-term loan agreement to enable HBL to on-lend to its customers.
The first loan disbursement (drawdown) took place on January 31, 2019. Additional disbursements (drawdowns) were permitted until January 31, 2023. Cumulative disbursements amounted to $62.890 million in 2019, $165.975 million in 2020, and $170.975 million in 2021.
The borrower is responsible for making semi-annual repayments between January 31, 2023 and January 31, 2033.