| Funder | China Ministry of Commerce |
|---|---|
| Recipient Organization | Government of Cuba |
| Country | Cuba |
| Start Date | Jan 01, 2015 |
| End Date | Dec 23, 2026 |
| Duration | 4,374 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 69158 |
Chinese Government provides $22.95 million USD loan for 29 MW Solar Power Project On March 2, 2015, the Chinese and Cuban governments signed an Exchange of Letters for the implementation of solar power station projects.
Cuba's Ministry of Energy and Mines planned to install photovoltaic facilities, capable of 29 MW in total, on five Cuban solar farms through a $24,590,000 grant and $22,950,000 soft loan, both provided by the Chinese Ministry of Commerce (MOFCOM). The grant is captured in linked Record ID#54762.
The project management unit is China Qiyuan Engineering Design and Research Institute Co., Ltd., and the project general contractor is China Hydropower Engineering Consulting Group Company. The first stage of this project involved the construction of two photovoltaic plants with a combined capacity of 9 MW.
The pair includes a 4 MW solar farm in the Pinar del Rio province and a 5 MW plant in Cienfuegos province, the latter being the largest facility of its kind in Cuba.
Construction of the power plants began on 18 November, 2016 and was completed and successfully passed technical acceptance on 12 April, 2018.
On 26 April, 2018, the ceremony for the completion and handover of the photovoltaic power plants was held at the site of the 5MW project in the town of Yaguaramas, Cienfuegos Province, Cuba. Solar parks will continue to be constructed in the Cienfuegos province until 2030. China will provide the technology while Cuba will take care of the physical construction.