| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Thermal Power Plants Holding Company (TPPH) |
| Country | Iran |
| Start Date | Jan 01, 2017 |
| End Date | Sep 06, 2026 |
| Duration | 3,535 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 67004 |
China Eximbank provides $613 million loan for Abadan Combined Cycle Power Plant Project In 2017, China Eximbank issued a $613 million loan for the Abadan Combined Cycle Power Plant Project.
The purpose of this project is to support a power plant that is located 10 km northeast of the city of Abadan in Khuzestan Province. The locational coordinates of the plant, which is situated at km 9 along the Abadan-Mahshahr Road, are 30.402, 48.358.
The project involves the installation of two E-type 160-MW steam turbines, HRSG (heat recovery system generator) with supplementary firing, ACC cooling system, and a 400-kv substation. MAPNA Combined Cycle Power Plants Construction & Development (MD-2) Company is the contractor of the project. The second steam unit was delivered on January 12, 2020.
The steam portion was constructed as an addendum to the original contract for construction of Abadan thermal power plant, signed in 2006. Thermal Power Plants Holding Company is the client of the project and Moshanir serves as the consultant and supervisor.
The power plant's electricity generation capacity is expected to reach 815 megawatts (MW) and the plant's efficiency is expected to be enhanced by 50 percent once the two steam units (each with a 160 MW capacity) go into operation.
Thermal Power Plants Holding Company (TPPH)