| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Power Control Engineering Company |
| Country | Iran |
| Start Date | Jan 01, 2017 |
| End Date | Mar 05, 2029 |
| Duration | 4,446 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 66999 |
China Eximbank provides $326 million buyer’s credit loan for 448MW Zanjan 1 Gas-fired Combined Cycle Power Plant Project In 2017, China Eximbank issued a $326 million buyer’s credit loan agreement to Power Control Engineering Company for the 448MW Zanjan 1 Gas-fired Combined Cycle Power Plant Project.
A sovereign guarantee was provided for this loan.
The proceeds of the loan were used to be used by the borrower to partially financed an EPC contract with China National Electric Engineering Co (CNEEC), which was officially signed on August 28, 2015.
The purpose of the project is to construct a 448MW combined cycle power plant near the village of Chovrovk at the 75 km along the Zanjan-Tabriz highway. The construction of the plant is being implemented on a Build-Own-Operate (BOO) basis. CNEEC is the EPC contractor responsible for implementation. PowerChina also seems to be involved (most likely as a subcontractor).
Construction began on August 25, 2016 and the project duration was estimated to be 48 months. But it is unclear whether/when this project was completed.