Loading…
Loading grant details…
| Funder | Sinohydro Corporation Limited |
|---|---|
| Recipient Organization | Zambia Electricity Supply Corp. (ZESCO) |
| Country | Zambia |
| Start Date | Oct 17, 2016 |
| End Date | Feb 05, 2032 |
| Duration | 5,589 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 66848 |
Sinohydro provides $29 million supplier's credit for Musonda Falls Hydroelectric Power Plant Upgrading Project According to the ZESCO 2016 Integrated Report (p. 86), on October 17, 2016, Sinohydro Corporation Ltd. and ZESCO Ltd. signed a $29 million USD bridge loan facility for the Musonda Falls Hydroelectric Power Plant Upgrading Project.
This supplier's credit loan carried a 7% interest rate.
The maturity was from the date when the loan agreement came into effect (October 17, 2016) until the date when funds became available to ZESCO Limited from a financial institution. ZESCO obtained financing from ICBC on January 26, 2017 (Record ID#57560). Principal and interest was repaid immediately after ZESCO and ICBC signed the loan agreement.
Therefore, the Sinohydro supplier's credit loan maturity was approximately 3 months or 0.25-years. In 2017, the balance stood at $16.9 million USD. It is unclear whether the full $29 million USD was drawn down. The Musonda Falls Hydroelectric Power Plant is located in Musonda Falls within Mwense District and Luapula Province.
It is a source of power supply to seven districts in the province—namely, Chiengi, Kawambwa, Mwense, Chipili, Chembe, Nchelenge and Samfya. The purpose of this project was to upgrade the Musonda Falls Hydroelectric Power Plant from 5MW to 10MW.
This increase in local power capacity also added to the national grid capacity, thereby supporting the fishing industry, farming activities and potential mining activities in nearby communities. In 2015, Sinohydro won the 18-month contract for project implementation. Sinohydro had previously provided another bridging loan in 2015 (see Record ID#57565) for the same project.
As of 2017, this project had achieved a 99% completion rate.
Turbine-Generator Units 6 and 7 had completed their commissioning tests and reliability runs, but commissioning tests and reliability runs for Turbine-Generator Units 1 to 5 were still ongoing by the end of 2017. The scheduled project handover date of November 18, 2017 was not achieved.
However, a 2018 Energy Sector Report published by Zambia’s Energy Regulation Board (ERG) indicates that ‘[t]he increase in [power] generation in 2018 is attributed to the [upgrading] of Musonda Falls Power Station’, which suggests that this hydroelectric power plant project was completed and put into operation in 2018.
1. The Chinese project title is 穆松达水电站7台机组 共10MW.
Zambia Electricity Supply Corp. (ZESCO)
Complete our application form to express your interest and we'll guide you through the process.
Apply for This Grant