Loading…
Loading grant details…
| Funder | Industrial and Commercial Bank of China (ICBC) |
|---|---|
| Recipient Organization | Brown Coal Mines Banovići (RMU Banovići) |
| Country | Bosnia and Herzegovina |
| Start Date | Jul 01, 2016 |
| End Date | Aug 02, 2028 |
| Duration | 4,415 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 66348 |
ICBC provides EUR 259.25 million loan for 350 MW Banovići Thermal Power Plant Project In November 2015, Brown Coal Mines "Banovići“, joint-stock company (or RMU Banovići) — a state-owned company — and Dongfang Electric Corporation Limited (DEC) signed a strategic cooperation agreement regarding the 350 MW Banovići Thermal Power Plant Project.
In the event that it was awarded an EPC contract for the 350 MW Banovići Thermal Power Plant Project, DEC agreed to make efforts to facilitate a syndicated loan from China Eximbank, ICBC and Raiffeisen Bank International AG to cover 85% of the of the cost of the EPC contract. RMU Banovići and DEC later signed an EPC contract on November 24, 2015.
Then, in July 2016, a project financing agreement was signed by RMU Banovići, ICBC, and DEC.
ICBC reportedly agreed to provide an EUR 259.25 million loan that would finance 85% of the cost of an EUR 305 million commercial contract between RMU Banovići and DEC.
The borrower was also reportedly required to buy a credit insurance policy from Sinosure.
However, this project subsequently encountered a variety of implementation difficulties and its overall cost escalated to EUR 412.4 million.
As of 2018, RMU Banovići and ICBC seemed to be renegotiating their financing agreement and potentially involving a broader set of banks. An environmental permit was issued for this project on January 11, 2016.
However, in February 2017 the EU Energy Community ruled that the Banovići Thermal Power Plant would be considered a new plant under the Industrial Emissions Directive (IED) Chapter III, and would therefore need to comply with the stricter emission limit values for plants that entered operation after January 2, 2019, requiring amendments to the permit for the plant issued by the Ministry that did not specify this requirement.
The decision came in response to a July 2016 complaint filed by the environmental NGO Ekotim.
In December 2017, the Federal Ministry for Spatial Planning in Bosnia-Herzegovina decided not to issue a new construction permit for the 350 MW Banovići Thermal Power Plant Project, noting that several key issues such as water supply, coal supply, wastewater, flue gases and ash disposal had not been resolved.
A lawsuit challenging the plant's environmental permit from the Federal Ministry of Environment and Tourism, issued in January 2016, was ongoing.
Then, on May 21, 2019, it was reported that the Government of the Federation of Bosnia and Herzegovina (FBiH) had tasked the EPBiH (the state-owned power utility) ‘to accelerate all activities related to the projects for the construction of new units at existing coal-fired thermal power plants Tuzla (unit 7) and Kakanj (unit 8), as well as the project for the construction of Banovici [Thermal Power Plant] near the coal mine of the same name.’ In September 2019, RMU Banovici was denied a water permit for the coal plant, on the grounds that the application did meet the required conditions for a planned water reservoir.
Brown Coal Mines Banovići (RMU Banovići)
Complete our application form to express your interest and we'll guide you through the process.
Apply for This Grant