| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Iran Water and Power Resource Development Co (IWPC) |
| Country | Iran |
| Start Date | Jan 01, 2013 |
| End Date | May 23, 2030 |
| Duration | 6,351 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 66040 |
Chinese Government provides a loan for the 400 MW Khersan-3 Dam and Hydropower Plant Project In 2013, an unspecified Chinese Government institution extended a loan — through a line of credit — to Iran for the 400 MW Khersan-3 Dam and Hydropower Plant Project.
It is known that the total cost of the commercial contract for the 400 MW Khersan-3 Dam and Hydropower Plant Project was $44 million.
The proceeds of the loan were used to finance the commercial contract that Iran Water and Power Resources Development Company (IWPCO) — an Iranian state-owned enterprise — signed with a consortium consisting of Iranian companies Tana Energy, Jihad Water Resources Development Co., Parhoon Tarh, and Chinese state-owned firms China CAMC Engineering Co., Ltd. and SUMEC Group Corporation (SUMEC).
The purpose of this project was to construct a dam located approximately 45 kilometers southeast of the city of Lordegan, in Chahar Mahal and Bakhtiary province, upstream from the Karun-IV Dam. Construction began on April 3, 2013, with a 60-month (5-year) contract period. The dam was ultimately completed on September 5, 2019.