| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Vietnam Electricity (EVN) |
| Country | Viet Nam |
| Start Date | Apr 04, 2007 |
| End Date | Sep 09, 2033 |
| Duration | 9,655 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 65941 |
China Eximbank provides $355 million buyer's credit loan for 600MW Quang Ninh 2 Coal-Fired Power Plant Construction Project On April 4, 2007, the Export-Import Bank of China and Vietnam Electriity (EVN) signed a $355,793,000 buyer's credit loan (BCL) agreement (BLASH 2007003) for the 600MW Quang Ninh 2 Coal-Fired Power Plant Construction Project.
The loan’s final maturity date is 2023.
The borrower was responsible for making 20 consecutive, semi-annual principal payments to the lender (after the expiration of the grace period).
EVN on-lent the proceeds of the China Eximbank loan to Quang Ninh Thermal Power Joint Stock Company (QTP JSC), a project company that is jointly owned by EVN (80%), Vinacomin (15%), and Vinaconex (5%).
The proceeds of the loan were to be used by the ultimate borrower to partially finance a $418 million engineering, procurement, and construction (EPC) contract signed on November 16, 2006 with Shanghai Electric Group Company Limited. Sinosure provided buyer’s credit insurance.
The loan was also collateralized with specific assets, facilities, and equipment of the Quang Ninh 1 Coal-Fired Power Plant and the Quang Ninh 2 Coal-Fired Power Plant (owned by Quang Ninh Thermal Power Joint Stock Company).
The total collateral value of these items (as of June 30, 2022) was VND 18,790,866,943,157 (equivalent 78.67% of the total value of the mortgaged assets).
The purpose of the project was to construct a 600MW coal-fired power plant — with two, 300MW power generation units (Unit 3 and Unit 4) — in Hà Khánh ward, Hạ Long city, and Quảng Ninh province. Shanghai Electric Group Company Limited was the EPC contractor responsible for implementation. Construction began on May 28, 2007.
Unit 3 was connected to the national grid on December 13, 2012. It secured a temporary Acceptance Certificate (PAC) certificate on January 1, 2014. Unit 4 was connected to the national grid on September 9, 2013. It secured a temporary Acceptance Certificate (PAC) certificate on March 16, 2014. Units 3 and 4 began commercial operations on June 1, 2015.