Completed Mixed AidData Chinese Aid

China Eximbank provide $45.6 million preferential buyer's credit for 23MW Xeset 3 Hydropower Project

$45.66M USD

Funder Export-Import Bank of China (China Eximbank)
Recipient Organization Électricité du Laos (EDL)
Country Lao People's Democratic Republic
Start Date Jan 01, 2014
End Date Jul 09, 2032
Duration 6,764 days
Number of Grantees 1
Roles Recipient
Data Source AidData Chinese Aid
Grant ID 64819
Grant Description

China Eximbank provide $45.6 million preferential buyer's credit for 23MW Xeset 3 Hydropower Project In 2014, China Eximbank and Électricité du Laos (EDL) — the state corporation of Laos that owns and operates the country's electricity generation, electricity transmission and electricity distribution assets — signed a $45.657 million preferential buyer's credit (PBC) agreement for the 23MW Xeset 3 Hydropower Project.

📋 Loan / Grant Terms
📅 Maturity23.0095 years
⏳ Grace Period6.2144 years
💹 Interest Rate2%

The borrower was expected to use the proceeds of the PBC to finance approximately 90% of the $50.73 million cost of a commercial (EPC) contract between EDL and NORINCO International Co., Ltd.

In order to secure repayment of the loan, the borrower (EDL) was responsible for depositing revenues into an escrow account.

The purpose of the project was to construct a 23MW hydropower plant on the Xeset river between Saravan and Champassak provinces, about 750 kilometers from Vientiane. The exact locational coordinates of the power plant are 15.342113°N 106.31115°E. Upon completion, the plant was designed to produce 80 million kilowatt hour (kWh) per year.

The main components included an inter-basin water transfer system, a dam water retaining system, water diversion, and a power generation and transmission system. NORINCO International Co., Ltd. was the EPC contractor responsible for implementation. Construction officially began on January 18, 2014.

The first power generating unit of the hydropower station successfully passed a 72 hour trial operation on July 28, 2016, after which point it started to generate electricity 5 months ahead of schedule. A project completion ceremony was held on or around January 9, 2017. The originally anticipated project completion date was January 17, 2017.

There are multiple indications that the China Eximbank loan for this project may have financially underperformed vis-a-vis the original expectations of the lender. In 2020, the Laotian authorities urgently sought debt relief from China Eximbank.

At that time, the gross reserves of the Bank of Laos stood at only 1.5 months of import cover and credit rating agencies warned of a high default probability.

In 2020, China Eximbank agreed to reprofile multiple loan agreements that it had previously signed with the Government of Laos (as captured via Record ID#96464).

These debt service payment deferrals lasted for approximately 4-years (2020 and 2023) and provided approximately $1.892 billion of cash flow relief ($1.422 billion in deferred principal payments and $470 million in deferred interest payments). Deferred principal and interest repayments in 2020 were worth $202 million.

Deferred principal and interest payments were worth $426 million in 2021. Deferred principal and interest payments were worth $594 million in 2022. Deferred principal and interest payments were worth $670 million in 2023.

Additionally, according to a report published by the World Bank in April 2022, ‘[t]he energy sector, mostly represented by Électricité du Laos (EDL), accounted for over 30 percent of total PPG debt in 2021. […] EDL’s debt service obligations [were] still unsustainable [at the time], with future debt service accounting for about two fifths of EDL’s total operating revenue.’ In September 2020, a Chinese state-owned enterprise purchased a major public infrastructure asset in Laos—a large part of the country’s electricity transmission grid—from EDL as part of an apparent debt-for-equity swap.

China Southern Power Grid Co. and EDL established a joint venture known as Électricité du Laos Transmission Company Limited (EDLT).

China Southern Power Grid Co. purchased a 90% ownership stake in EDLT in exchange for a $600 million fee (equity infusion).

Then, in March 2021, EDLT signed a 25-year concession agreement, which made it responsible for management of the country’s high-voltage transmission network above 230 kilovolts.

Independent observers suggested at the time that EDL would likely use the $600 million upfront payment from China Southern Power Grid Co. to service its outstanding debts to Chinese creditors, although this has not been independently confirmed.

📋 Staff Comments
  1. The Chinese project title is 赛德3水电站.
  2. According to the World Bank's Debtor Reporting System (DRS), the weighted average maturity of all official sector lending from Chinese creditors to government and government-guaranteed borrowing institutions in Laos was 23.0095-years in 2014. AidData estimates the maturity of the China Eximbank loan that supported the 23MW Xeset 3 Hydropower Project by using this figure. See https://www.dropbox.com/scl/fi/uno1hf2pjg3nfz78h72c6/Private-and-Official-Sector-PRC-Borrowings-and-Borrowing-Terms-of-Lao-PDR-September-2024.xlsx?rlkey=s7eas067aykllu1lik074l5x5&dl=03. According to the World Bank's Debtor Reporting System (DRS), the weighted average grace period of all official sector lending from Chinese creditors to government and government-guaranteed borrowing institutions in Laos was 6.2144-years in 2014. AidData estimates the grace period of the China Eximbank loan that supported the 23MW Xeset 3 Hydropower Project by using this figure. See https://www.dropbox.com/scl/fi/uno1hf2pjg3nfz78h72c6/Private-and-Official-Sector-PRC-Borrowings-and-Borrowing-Terms-of-Lao-PDR-September-2024.xlsx?rlkey=s7eas067aykllu1lik074l5x5&dl=04. According to the World Bank's Debtor Reporting System (DRS), the weighted average interest rate of all official sector lending from Chinese creditors to government and government-guaranteed borrowing institutions in Laos was 2% in 2014. AidData estimates the interest rate of the China Eximbank loan that supported the 23MW Xeset 3 Hydropower Project by using this figure. See https://www.dropbox.com/scl/fi/uno1hf2pjg3nfz78h72c6/Private-and-Official-Sector-PRC-Borrowings-and-Borrowing-Terms-of-Lao-PDR-September-2024.xlsx?rlkey=s7eas067aykllu1lik074l5x5&dl=0
📚 Sources & References
  • Minutes of the Annual General Shareholders' Meeting for the Year 2015
  • 中企助力老挝打造“东南亚蓄电池”
  • 赛德3,一带一路上的又一颗珍珠
  • 中国在老第二个出口卖信项目赛德2水电站竣工交付
  • Lao Xeset 3 hydropower project officially launched
  • 赛德3,北方国际的又一颗珍珠——老挝缅甸的“北方印记”(一)
  • The Xeset 3 hydropower project officially launched, - 王粤涛总经理访问老挝并出席赛德3水电站竣工典礼 -
  • Adviser Profile
  • The Xeset 3 hydropower project officially launched
  • DEAL LIST: FOCUS ON ENERGY
  • MINING AND INFRASTRUCTURE
  • Credit crunch: Chinese infrastructure lending and Lao sovereign debt, - Laos XESET 3 Hydropower Project -, - The First Unit of Laos XESET 3 Hydropower Station Was Put Into Operation Successfully -
  • Chinese-built hydropower project handed over to Laos
  • GeoHack - Xeset 3 Dam, - President Wang Yuetao Paid a Visit to Laos and Attended the Opening Ceremony of Xeset3 Hydropower Station -
  • BU_PITCH_ENGLISH_2019-clean5.xlsx
  • China's Global Energy Finance: Laos
  • Deal List: Focus on Energy
  • Mining and Infrastrcuture Loan applications and disbursements are still being received and processed as the projects continue to evolve. Ongoing monitoring and evaluation are in place to ensure project continuity.
All Grantees

Électricité du Laos (EDL)

Advertisement
Apply for grants with GrantFunds
Advertisement
Browse Grants on GrantFunds
Interested in applying for this grant?

Complete our application form to express your interest and we'll guide you through the process.

Apply for This Grant