| Funder | Bank of China (BOC) |
|---|---|
| Recipient Organization | An Khanh Thermal Power Joint Stock Company |
| Country | Viet Nam |
| Start Date | Jan 01, 2016 |
| End Date | Jun 15, 2029 |
| Duration | 4,914 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 64492 |
[Cancelled] Bank of China provides loan for 300MW An Khanh 2 Coal-Fired Power Plant Construction Project On December 22, 2011, Bank of China Zhejiang Branch, China Construction Bank, China Eximbank, and China Bank of Communications signed a a $143,055,000 syndicated buyer’s credit loan agreement with An Khanh Thermal Power Joint Stock Company — a project company and special purpose vehicle — for the 100MW An Khanh 1 Coal-Fired Power Plant Construction Project (captured in Record ID#35270).
In July 2010, An Khanh Thermal Power Joint Stock Company submitted construction plans for the 300MW An Khánh 2 Coal-Fired Power Plant.
Vietnam Prime Minister Nguyễn Tấn Dũng approved the second power generation unit in July 2011 and a construction license followed in October 2011.
Then, in 2016, Bank of China reportedly issued a loan for the 300MW An Khanh 2 Coal-Fired Power Plant Construction Project.
However, the Government of Vietnam subsequently listed this project as ‘cancelled’ in its Power Development Plan VII.
The total project cost was somewhere between $481 million and $531 million but it is unclear how much Bank of China was supposed to finance.
The Vietnamese project title is Nhiệt điện An Khánh 2.