| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Government of Laos |
| Country | Lao People's Democratic Republic |
| Start Date | Aug 11, 2009 |
| End Date | Apr 27, 2033 |
| Duration | 8,660 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 62991 |
China Eximbank provides $120 million loan for 230kV Hin Heup-Luangprabang 2 Power Transmission Line Project On August 11, 2009, Sinohydro Group Limited and Electricite du Laos signed a $129 million EPC contract for the 230kV Hin Heup-Luangprabang 2 Power Transmission Line Project.
China Eximbank subsequently provided a $120 million loan to the Government of Laos to partially finance the EPC contract. The loan carried a 2% interest rate. Its estimated maturity is 22.2696-years and its estimated grace period is 6.975-years.
The purpose of the project was to construct a 210 km 230kv electricity transmission line between the Hinheup hydroelectric dam in Vientiane province and Luang Prabang.
The project also involved the construction of two substations: one in Hin Heup, a district in Vientiane Province and another (known as ‘Luangprabang 2’) in Xieng Ngeun, a district in Luangprabang Province. Sinohydro Group Limited was the EPC contractor responsible for implementation. Construction began on November 8, 2010.
Then, on October 31, 2013, the Luangprabang 2 substation was successfully put into operation. This project appears to have reached completion. However, its precise implementation end date is unknown.
There are multiple indications that the China Eximbank loan for this project may have financially underperformed vis-a-vis the original expectations of the lender. In 2020, the Laotian authorities urgently sought debt relief from China Eximbank.
At that time, the gross reserves of the Bank of Laos stood at only 1.5 months of import cover and credit rating agencies warned of a high default probability.
In 2020, China Eximbank agreed to reprofile multiple loan agreements that it had previously signed with the Government of Laos (as captured via Record ID#96464).
These debt service payment deferrals lasted for approximately 4-years (2020 and 2023) and provided approximately $1.892 billion of cash flow relief ($1.422 billion in deferred principal payments and $470 million in deferred interest payments). Deferred principal and interest repayments in 2020 were worth $202 million.
Deferred principal and interest payments were worth $426 million in 2021. Deferred principal and interest payments were worth $594 million in 2022. Deferred principal and interest payments were worth $670 million in 2023.
Additionally, according to a report published by the World Bank in April 2022, ‘[t]he energy sector, mostly represented by Électricité du Laos (EDL), accounted for over 30 percent of total PPG debt in 2021. […] EDL’s debt service obligations [were] still unsustainable [at the time], with future debt service accounting for about two fifths of EDL’s total operating revenue.’ In September 2020, a Chinese state-owned enterprise purchased a major public infrastructure asset in Laos—a large part of the country’s electricity transmission grid—from EDL as part of an apparent debt-for-equity swap.
China Southern Power Grid Co. and EDL established a joint venture known as Électricité du Laos Transmission Company Limited (EDLT).
China Southern Power Grid Co. purchased a 90% ownership stake in EDLT in exchange for a $600 million fee (equity infusion).
Then, in March 2021, EDLT signed a 25-year concession agreement, which made it responsible for management of the country’s high-voltage transmission network above 230 kilovolts.
Independent observers suggested at the time that EDL would likely use the $600 million upfront payment from China Southern Power Grid Co. to service its outstanding debts to Chinese creditors, although this has not been independently confirmed.
Government of Laos