China Eximbank provides RMB 710 million government concessional loan for Port Moresby City Roads Project On March 21, 2014, the Export-Import Bank of China and the Government of Papua New Guinea signed an RMB 710 million ($110 million) government concessional loan (GCL) agreement for the Port Moresby City Roads Project (Lot 1 and Lot 2).
The proceeds of the GCL were to be used by the borrower to finance a commercial contract that the Government of Papua New Guinea signed with China Harbour Engineering Co., Ltd. on June 14, 2013.
The purpose of the project was to (a) reconstruct an 13 km road (Baruni Road) from Konedobu to Baruni and Gerehu (Lot 1) and (b) reconstruct an 8.7 km road from Gerehu to the 9-Mile Arterial Road (Lot 2). CHEC was the contractor responsible for implementation.
A project commencement ceremony took place on May 7, 2014, and Papua New Guinea's Minister of Transport conducted an on-site project inspection on November 30, 2015. The project was originally scheduled for completion in July 2016.
However, it was ultimately completed on June 22, 2017. 205 Chinese workers and 460 PNG workers were involved in the implementation of this project.