| Funder | China Ministry of Commerce |
|---|---|
| Recipient Organization | Government of Sierra Leone |
| Country | Sierra Leone |
| Start Date | Sep 26, 2016 |
| End Date | Jan 15, 2028 |
| Duration | 4,128 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 62517 |
In September 26, 2016, the Chinese Embassy in Sierra Leone reported that it signed a supplementary agreement with Sierra Leone’s Ministry of Energy for the construction of the China-aided Port Loko and Charlotte Transmission and Distribution Network Project.
This project involved the installation of two substations, 21 km of 11kV power transmission lines, 3 km of 415V power transmission lines, 20 transformers, and a high-voltage switchgear. The total cost of the project was RMB 49,723,500 (approximately $7.02 million). Shanxi Construction Investment Group Co., Ltd. was the contractor responsible for Implementation.
Construction began in November 17, 2016 and ended on December 12, 2017. The handover ceremony occurred on December 22, 2017.
The Chinese embassy identifies the project site locations as Port Loko and Charlotte, but Shanxi Construction Investment Group Co., Ltd. identifies the project site locations as Port Loko, Freetown and Makali. The nature and size of the Chinese Government financial commitment for this project is unknown.