Loading…
Loading grant details…
| Funder | China Ministry of Commerce |
|---|---|
| Recipient Organization | Government of Equatorial Guinea |
| Country | Equatorial Guinea |
| Start Date | Jan 01, 2008 |
| End Date | May 19, 2033 |
| Duration | 9,270 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 62257 |
In 2008, China’s Ministry of Commerce provided a grant to the Government of Equatorial Guinea for the Nkolombong (Bata) Electricity Substation Reconstruction Project. The monetary value of this grant commitment is unknown. The project sought to increase the distribution voltage of an electricity substation from 15kV to 20kV.
The project commenced on August 1, 2009 and it was completed on November 7, 2009. It later received an acceptance certificate on April 8, 2010.
The Chinese project title is 援赤几恩科隆博变电站改造项目 or 赤道几内亚恩科隆博变电站变压器改造项目.The Spanish project title is El Proyecto sobre la reforma de equipos de la subestación eléctrica de Nkolombong (Bata).
Government of Equatorial Guinea
Complete our application form to express your interest and we'll guide you through the process.