| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Banchuan Development Co., Ltd. (BCD)|Benjarat Development Co., Ltd. (BJRD)|Nayangklak Development Co., Ltd. (NYKD)|Nayangklak Wind Power Co., Ltd. (NWP)|Pongnok Development Co., Ltd. (PND) |
| Country | Thailand |
| Start Date | Jan 01, 2017 |
| End Date | Mar 16, 2031 |
| Duration | 5,187 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 62177 |
China Eximbank provides loan for 260MW Hanuman Wind Farm Project Thailand-based, publicly-held Energy Absolute (EA) Public Company Limited is the parent company for the following separate project companies: 1) Nayangklak Development Co., Ltd. (“NYKD”), 2) Pongnok Development Co., Ltd. (“PND”) 3) Nayangklak Wind Power Co., Ltd. (“NWP”), 4) Benjarat Development Co., Ltd. (“BJRD”), and 5) Banchuan Development Co., Ltd. (“BCD”).
These subsidiaries are responsible for designing, financing, implementing, and maintaining five separate wind farms: Hanuman 1 (45MW), Hanuman 5 (48MW), Hanuman 8 (45MW), Hanuman 9 (42MW), Hanuman 10 (80MW) in Thailand.
In 2017, China Eximbank provided debt financing to one or more of EA's project companies for the 260MW Hanuman Wind Farm Project.
The proceeds of the China Eximbank loan appear to have been used by the borrower(s) to finance several commercial contracts between PowerChina and Energy Absolute (EA) Public Company Limited.
However, it is known that the loan was supported by a Sinosure credit insurance policy.
The purpose of the project was to construct a 45MW wind farm in Thebsathit District, Chaiyaphum Province (Hanuman 1), a 48MW wind farm in Thebsathit District, Chaiyaphum Province (Hanuman 5), a 45MW wind farm in Thebsathit District, Chaiyaphum Province (Hanuman 8), a 42MW wind farm in Thebsathit District, Chaiyaphum Province (Hanuman 9), and an 80MW wind farm in Bamnetnarong District, Chaiyaphum Province (Hanuman 10).
PowerChina was the EPC contractor responsible for implementation. The project commenced on or around April 25, 2018. It was completed on January 23, 2019.
The electricity output from the project was expected to be sold to the Electricity Generating Authority of Thailand (EGAT), per the terms of a power purchase agreement (PPA) that was signed on September 25, 2013.
Banchuan Development Co., Ltd. (BCD)|Benjarat Development Co., Ltd. (BJRD)|Nayangklak Development Co., Ltd. (NYKD)|Nayangklak Wind Power Co., Ltd. (NWP)|Pongnok Development Co., Ltd. (PND)