| Funder | China Development Bank (CDB) |
|---|---|
| Recipient Organization | PNG Hydro Development Ltd. (PNGHDL)) (PNG Hydropower) |
| Country | Papua New Guinea |
| Start Date | Jan 01, 2017 |
| End Date | Aug 29, 2032 |
| Duration | 5,719 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 61212 |
China Development Bank provides $260 million loan for 50MW Edevu Hydropower Plant Project In November 2014, China Railway Construction Engineering Group, AG Investment Limited, and China Development Bank Corporation signed a project investment and financing framework for the 50MW Edevu Hydropower Plant Project.
Then, in 2017, China Development Bank signed a $260 million loan agreement with PNG Hydro Development Company Limited (PNGHDCL or PNGHDL or 巴布亚新几内亚水电开发公司) — a special purpose vehicle (SPV) — for the 50MW Edevu Hydropower Plant Project.
In 2017, China Eximbank also expressed interest in lending to PNGHDL for the 50MW Edevu Hydropower Plant Project, but it is unclear if a loan agreement with China Eximbank was ever finalized.
PNGHDL also signed a power purchase agreement with PNG Power (PPL) — a state-owned power utility — and under the terms of this agreement PNGHDL agreed to produce electricity and sell it to PPL.
The purpose of the project is to construct a 50MW hydropower plant near the village of Edevu within Kairuku-Hiri District in Central PNG.
The project involves the construction of a 55 meter high geomembrane faced rockfill dam, overflow chute spillway, and a 51 MW surface power station at the toe of the dam.
The project site is located at 147°20ʹ23.5ʹ east longitude and 9°11ʹ23.6ʹ’ south latitude in the middle reaches of the Brown River in the northern part of PNG's capital Port Moresby.
Upon completion, it is expected that the power plant will generate between 50MW and 54MW of additional power for the capital city Port Moresby, as well as provide residents with an alternative water source.
Hunan Hong Yu Engineering Group Ltd., China Railway Construction Engineering Group, AG Investment Limited and SMEC are the contractors responsible for project design and implementation. A formal groundbreaking ceremony took place on February 6, 2017. Then, in late May 2017, the construction of a 500 meter underground diversion tunnel was completed.
On August 15, 2019, China Energy Gezhouba Group signed a contract for project management (PMC) with PNGHDL.
The project was originally expected to commence on April 7, 2015 and reach completion on April 30, 2016, but the project completion date was later pushed out to June 2022. As of October 2022, the project was still not complete.
PNG Hydro Development Ltd. (PNGHDL)) (PNG Hydropower)