| Funder | China Ministry of Commerce |
|---|---|
| Recipient Organization | Government of Kenya |
| Country | Kenya |
| Start Date | Aug 02, 2010 |
| End Date | Jul 10, 2027 |
| Duration | 6,186 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 60195 |
On August 2, 2010, China's Ministry of Commerce provided a $2,739,876 grant to the Kenyan Government for the refurbishment of the Moi International Sports Centre in Kasarani, a suburb of Nairobi. An Exchange of Letters for Maintenance of the Moi International Sport Center was signed during H.E. President Hu Jintao’s visit to Kenya in April 2006.
Sheng-Li Engineering Construction Company Ltd. ((胜利油田胜建集团) was the contractor.
The project's original timeline was for construction to last 12 months from December 24, 2009, to December 23, 2010, but Sheng-Li Engineering Construction Company Ltd. extended work until June 2012. The stadium was closed in January 2010 for renovation works. On June 2, 2012, the Moi International Sports Centre reopened.
A $12,264,851.49 loan was provided by the Chinese Government in August 2010 for the same project (see #1265). The Moi International Sports Centre was originally built with RMB 200 million in grant funding the Chinese government for the All Africa Games in 1987.