| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Sino-Congolais des Mines (Sicomines SARL) |
| Country | Democratic Republic of the Congo |
| Start Date | Jan 01, 2017 |
| End Date | Dec 15, 2027 |
| Duration | 4,000 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 59533 |
In 2008, China Eximbank issued a $3.003 billion general buyer's credit loan to Sino–Congolais des Mines (Sicomines SARL) — a joint venture — to finance infrastructure projects in the DRC (as captured via Record ID#450).
All subsidiary borrowings under the (government-guaranteed) general buyer's credit loan agreement were to be repaid with revenues from mining projects managed by Sicomines SARL.
All infrastructure projects supported through the general buyer's credit loan were part of the so-called “Sino-Congolese Programme." One of the subsidiary projects under the ‘Sino-Congolese Programme’ was the funding of the technical studies for the Bukavu Stadium Construction Project in 2017.
Technical studies focused on topographical, geotechnical, and photogrammetry analysis. Democratic Republic of Congo Agence Congolaise des Grands Travaux (ACGT) was the implementing agency. The groundbreaking ceremony was held on January 6, 2018. It is unclear whether the project is ongoing or complete.
The nature of the financial commitment for this project is also unknown.