Loading…
Loading grant details…
| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Government of Djibouti |
| Country | Djibouti |
| Start Date | Dec 25, 2017 |
| End Date | Apr 17, 2028 |
| Duration | 3,766 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 59453 |
China Eximbank provides RMB 303.6 million government concessional loan for Phase 2 of the Ethiopia-Djibouti Water Pipeline Project On September 2, 2012, a Memorandum of Understanding (MOU) between the Government of the Federal Democratic Republic of Ethiopia and the Republic of Djibouti on Supply of Water to Djibouti was signed.
Then, on September 11, 2013, China Eximbank and the Djiboutian Ministry of Finance signed a $322,050,000 (FDJ 57,163,000,000) preferential buyer’s credit (PBC) agreement for Phase 1 of the Ethiopia-Djibouti Water Pipeline Project.
The loan also carried a guarantee from an unspecified guarantor.
The proceeds of the loan (captured via Record ID#59425) were to be used by the borrower to partially finance a $339 million commercial contract between Office National De L'Eau Et De L'assainissement De Djibouti (ONEAD) and CGC Overseas Construction Co. (CGCOC) Ltd., which was signed on April 11, 2013.
The Government of Djibouti was responsible for the remainder of the commercial contract cost (approximately $17 million).
According to Djibouti’s Ministry of Economy, Finance, and Industry, the PBC (loan) ultimately achieved a 108.2% disbursement rate (FDJ 61,826,000,000).
Phase 1 of the Ethiopia-Djibouti Water Pipeline Project involved the construction of a 63-mile long water pipeline from the Ethiopian town of Hadagalla into the interior of Djibouti, where it was expected to supply safe drinking water to 700,000 residents of Ali-Sabieh region, Dikhil region, Arta region and Djibouti City.
CGC Overseas Construction Co. (CGCOC) Ltd. was the contractor responsible for project implementation. Its work was overseen by Office National De L'Eau Et De L'assainissement De Djibouti (ONEAD).
The originally envisaged project implementation start and end dates (as specified in the April 11, 2013 commercial contract) were July 1, 2015 and March 30, 2018. A groundbreaking ceremony took place on March 22, 2015. However, Phase 1 implementation did not commence until March 30, 2015. As of February 2017, ONEAD reported that Phase 1 had achieved an 87% completion rate.
CGC Overseas Construction Co. (CGCOC) Ltd encountered some difficulties during project implementation, including electricity power outages that made it impossible to transmit the water through the pipeline.
CGC Overseas Construction Co. (CGCOC) Ltd was reportedly forced to spend more money than originally anticipated on diesel generators due to power shortages needed to pump the water. Phase 1 was officially completed and handed over to the local authorities on June 30, 2017.
Then, on December 25, 2017, China Eximbank and the Government of Djibouti signed an RMB 303,660,000 (or $43.38 million USD or 8,460,208,609 DJF) government concessional loan (GCL) agreement for Phase 2 of the Ethiopia-Djibouti Water Pipeline Project.
The Djiboutian legislature ratified the GCL agreement on June 25, 2018.
The purpose of Phase 2 is to provide electricity to various sites along a 63-mile-long water pipeline that runs from the Ethiopian town of Hadagalla into the interior of Djibouti, where it is expected to supply safe drinking water to 700,000 residents of Ali-Sabieh region, Dikhil region, Arta region and Djibouti City.
CGC Overseas Construction Co. (CGCOC) Ltd. is the contractor responsible for the implementation of Phase 2. However, AidData has not yet identified any evidence that Phase 2 implementation has commenced.
Government of Djibouti
Complete our application form to express your interest and we'll guide you through the process.
Apply for This Grant