| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Sino-Congolais des Mines (Sicomines SARL) |
| Country | Democratic Republic of the Congo |
| Start Date | Jan 01, 2011 |
| End Date | Apr 16, 2033 |
| Duration | 8,141 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 59427 |
[Sino-Congolese Programme] China Eximbank provides $19.3 million loan for Boulevard 30 Juin Construction (Lot 2) Project In 2008, China Eximbank issued a $3.003 billion general buyer's credit loan to Sino–Congolais des Mines (Sicomines SARL) — a joint venture — to finance infrastructure projects in the DRC (as captured via Record ID#450).
All subsidiary borrowings under the (government-guaranteed) general buyer's credit loan agreement were to be repaid with revenues from mining projects managed by Sicomines SARL.
All infrastructure projects supported through the general buyer's credit loan were part of the so-called “Sino-Congolese Programme." One of the subsidiary loans issued as part of the 'Sino-Congolese Programme' was a $19,341,204.19 loan for Boulevard 30 Juin Construction (Lot 2) Project. The loan ultimately achieved a disbursement rate of 97.4% ($18,856,314.75 out of $19,341,204.19).
The purpose of the Boulevard 30 Juin Construction (Lot 2) Project was to improve traffic flow and conditions on the 2.5km stretch of Boulevard du 30 Juin between Central Station and Kintambo Magasin. China Railway Engineering Corporation (CREC) was the contractor responsible for implementation. It was awarded a contract (ID#ACGT/DG/DT/2/2004/2009) on December 9, 2009.
Construction began on February 8, 2011 and ended on July 23, 2014. The project’s originally scheduled completion date was January 25, 2013.
Sino-Congolais des Mines (Sicomines SARL)