China Eximbank provides $49.33 million buyer’s credit loan for Lot 1 Beles-Bahir Dar 400kV Power Transmission Project (Linked to Record ID#45047)

$49.34M USD

Funder Export-Import Bank of China (China Eximbank)
Recipient Organization Commercial Bank of Ethiopia (CBE)
Country Ethiopia
Start Date Sep 23, 2008
End Date Oct 09, 2029
Duration 7,686 days
Number of Grantees 1
Roles Recipient
Data Source AidData Chinese Aid
Grant ID 59264
Grant Description

China Eximbank provides $49.33 million buyer’s credit loan for Lot 1 Beles-Bahir Dar 400kV Power Transmission Project In November 2006, China Eximbank and the Government of Ethiopia’s Ministry of Finance and Economic Development signed a $500 million buyer’s credit facility agreement (互惠贷款) — also known as a master loan framework agreement and a master facility agreement — for an unspecified set of development projects.

📋 Loan / Grant Terms
💰 Loan Amountfacility agreement (captured via Record ID#45047) carried the following borrowing terms: a 13-year maturity
📅 Maturity13 years
⏳ Grace Period4 years

All of the subsidiary loans were secured with (i.e., collateralized against) Ethiopia's export receipts to China, which at the time primarily consisted of sesame seed export receipts.

The buyer’s credit facility agreement also required that all Ethiopian exports (export receipts) to China to be overseen by the Commercial Bank of Ethiopia (CBE), the country’s largest state-owned financial institution.

As a source of collateral, the borrower was required to maintain a minimum cash balance in a debt service reserve account (DSRA) at the CBE.

The cash balance of the DSRA (escrow account) was $284,368,041 as of June 30, 2011, $308,914,767 as of June 30, 2012, $300,000,000 as of June 30, 2016, $300,000,000 as of June 30, 2017, $300,000,000 (ETB 8,260,410,000) as of June 30, 2018, $300,000,000 as of June 30, 2019, ETB 10,599,600,000 as of June 30, 2020, ETB 8,058,726,059 as of June 30, 2021, ETB 10,722,750,953 as of June 30, 2022, and ETB 9,832,603,839 as of June 30, 2023. 16 subsidiary loans for 16 different projects were reportedly approved under the buyer’s credit facility agreement. 16 subsidiary loans for 16 different projects were reportedly approved under the buyer’s credit facility agreement.

According to the Government of Ethiopia’s Aid Management Platform (AMP), China Eximbank, CBE, and Ethiopian Electric Power Corporation (EEPCo) — and Ethiopian state-owned enterprise — signed a subsidiary buyer’s credit loan worth approximately ETB 621,347,607 ($49,335,871.83) for the Lot 1 Beles-Bahir Dar 400kV Power Transmission Project on September 23, 2008.

The loan's first and last scheduled principal payment dates were March 31, 2012 and September 30, 2021, respectively. Its first and last scheduled interest payment dates were July 1, 2009 and September 30, 2022, respectively.

The borrower was expected to use the proceeds of the loan to finance approximately 85% of the cost of a commercial contract between EEPCo and Shanghai Electric Power Transmission and Distribution Engineering Co., Ltd., which was signed in August 2007.

According to the Government of Ethiopia’s AMP, the ETB 621,347,607 ($49,335,871.83) loan achieved a 64% disbursement rate, with China Eximbank making 4 loan disbursements (worth ETB 392,472,065) between 2009 and 2012: an ETB 220,368,488 disbursement on December 31, 2009, an ETB 68,814,286 disbursement on July 7, 2011, an ETB 3,247,423 disbursement on October 10, 2011, and an ETB 100,041,869 disbursement on January 8, 2012.

The purpose of the project was to construct a 67 km, 400 kV power transmission line that connects Tana Beles hydropower plant switchyard to Bahir Dar II substation. Its precise implementation start date is unknown. However, as of September 2010, the project had achieved a 75% completion rate. The project was officially completed and inaugurated on March 19, 2011.

It was originally scheduled for completion in June 2010.

There are some indications that the China Eximbank loan for the Lot 1 Beles-Bahir Dar 400kV Power Transmission Project financially underperformed vis-à-vis the original expectations of the lender.

According to the Government of Ethiopia’s Debt Management and Financial Analysis System (DMFAS), the borrower secured a 4.75-year maturity extension, with the loan's final maturity date reset from September 30, 2021 to June 30, 2026.

📋 Staff Comments
  1. The Chinese project title is 埃塞俄比亚400kV变电站和输电线路项目.
  2. For loan and debt rescheduling records with variable interest rates, AidData calculates the all-in interest rate at T0 based on the reference rate (such as LIBOR or EURIBOR) on the loan start date, plus any known margin. Please see the methodology for additional details.
  3. This buyer's credit loan from China Eximbank is not included in the database of Chinese loan commitments that SAIS-CARI released in 2020 and re-released in 2021. Nor is it included it in the China’s Overseas Development Finance Dataset that Boston University's Global Development Policy Center published in December 2020.
  4. This project was part of a larger, $168 million project with four sections (‘Lots’) — known as the Bahir Dar-Debre Markos-Addis Ababa (BBDA) Power Transmission Line and Substations Project, the BBDA Power Transmission Line and Substation Project, the BBDA Power Transmission and Transformation Project, or the Tana Beles to Addis Ababa 400 kV Power Transmission Line Construction Project — that involved the construction of a 400 km transmission line from the Tana Beles hydropower plant to Sululta substation through Bahir Dar and Debre Markos substations. The power transmission line has three sections: a 67 km section from Tana Beles hydropower plant switchyard to Bahir Dar II substation, a 193.77 km section from Bahir Dar II substation to Debre Markos substation, and a 215.43 km section from Debre Markos substation to Sululta substation.
  5. The AMP system identification number for the Lot 1 Beles-Bahir Dar 400kV Power Transmission Project is 8714327100834.
  6. 1 Ethiopian Birr (ETB) was equal to 0.081 United States Dollars (USD) in September 2009, which implies that the ETB 621,347,607 loan commitment recorded in the AMP was worth USD 50,329,156.16 at that time that it was contracted. However, AidData relies on the USD face value of the loan reported by MOFED through the following
📚 Sources & References
  • https://www.sciedupress.com/journal/index.php/jms/article/viewFile/25488/16079.7. According to CBE's financial statements for the year ending on June 30, 2012 (https://www.combanketh.et/cbeapi/uploads/2011_12_2037357399.pdf), 'CBE is the administrator of the total loan of USD 499,222,780, granted by EXIM Bank of China to the Ethiopian Electric Power Corporation (EEPCO) and Muger Cement Enterprise (MCE). The said loans are repayable by EEPCO and MCE to CBE in Birr over a period of ten years.'8. The loan identification number in the Government of Ethiopia’s Debt Management and Financial Analysis System (DMFAS) is 20776006 and the corresponding project name in DMFAS is ‘BELES-BAHERDAR LOT 1 SUBSTATIO’. See https://www.dropbox.com/scl/fi/7nrczfanixvivmiyzqx3i/MOFED-Loan-Level-Data-on-Borrowing-Terms-and-Loan-Performance-September-2024_OTHER_PUBLIC.xlsx?rlkey=5sqhh9ii4t3x8cmz0jf6s7cod&dl=09. As of September 2024, the Government of Ethiopia recorded the loan's all-in interest rate as 5.5% in DMFAS. See https://www.dropbox.com/scl/fi/7nrczfanixvivmiyzqx3i/MOFED-Loan-Level-Data-on-Borrowing-Terms-and-Loan-Performance-September-2024_OTHER_PUBLIC.xlsx?rlkey=5sqhh9ii4t3x8cmz0jf6s7cod&dl=010. More research is needed to identify the precise date on which the China Eximbank debt rescheduling agreement was signed. One source suggests that it may have come shortly after April 9, 2019 (see https://repub.eur.nl/pub/134509/final-thesis-valeria-lauria-nov-2020.pdf). Sources: Speech at the Inaugural Ceremony of BBDA Power Transmission Line and Substation Project by H.E. Ambassador Gu Xiaojie
  • Presentation For 4th AIPF -Shanghai Electric
  • 驻埃塞俄比亚大使顾小杰出席中方援建的输变电项目启用仪式
  • 中国进出口银行副行长一行参观埃塞电力项目现场
  • PREPARATORY SURVEY ON ADDIS ABABA TRANSMISSION AND DISTRIBUTION SYSTEM REHABILITATION AND UPGRADING PROJECT
  • Ethiopian Electric Power Corporation--Bahir Dar-Debre Markos-Addis Ababa 400kv, 400KV SUBSTATION AND POWER TRANSMISSION LINE PROJECT IN ETHIOPIA
  • ADDIS ABABA TRANSMISSION AND DISTRIBUTION SYSTEM REHABILITATION AND UPGRADING PROJECT (AATDRUP)
  • Ethiopia
  • Chinese firms sign massive power supply contracts, http://www.ethiopiainvestor.com/index.php?view=article&catid=69%2525252525253Aarchives&id=1625%2525252525253Alag-in-transmission-lines-compels-systematic-power-shedding-by-eepco&tmpl=component&print=1&page=&option=com_content&Itemid=88, http://www.shanghai-electric.com/en/business/service/electricalcompleteset/Pages/default.aspx
  • Ethiopia: Lag in Transmission Lines Compels Systematic Power Shedding
  • Ethiopia
  • China: Loan Deal For Power Line
  • Ethiopia
  • China sign 140m-US dollar loan accord for power, 2008
  • EPC of BBDA 400kV Transmission Line Project in Ethiopia.
  • 宝石风暴最新版本
  • A Survey of the Economic and Trade Relationships between China
  • India and Ethiopia
  • Lag in Transmission Lines Compels Systematic Power Shedding by EEPCo
  • Power projects proposed and under construction
  • Techno-Economic Comparisons of HVAC and Simultaneous AC-DC Transmission
  • 埃塞俄比亚BBDA 400kV输电线路EPC工程
  • LOT1 BELES-BAHAIRDAR 400KV POWER TRANSMISSION PROJECT
  • CBE Annual Report 2011-2012
  • CBE Annual Report 2010-2011
  • MOFED Loan-Level Data on Borrowing Terms and Loan Performance September 2024_PUBLIC Loan applications and disbursements are still being received and processed as the projects continue to evolve. Ongoing monitoring and evaluation are in place to ensure project continuity.
All Grantees

Commercial Bank of Ethiopia (CBE)

Advertisement
Apply for grants with GrantFunds
Advertisement
Browse Grants on GrantFunds
Interested in applying for this grant?

Complete our application form to express your interest and we'll guide you through the process.

Apply for This Grant