| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Sino-Congolais des Mines (Sicomines SARL) |
| Country | Democratic Republic of the Congo |
| Start Date | Aug 17, 2015 |
| End Date | May 09, 2030 |
| Duration | 5,379 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 59212 |
[Sino-Congolese Programme] China Eximbank provides $10 million loan for Phase 1 of Bukavu Stadium Construction Project In 2008, China Eximbank issued a $3.003 billion general buyer's credit loan to Sino–Congolais des Mines (Sicomines SARL) — a joint venture — to finance infrastructure projects in the DRC (as captured via Record ID#450).
All subsidiary borrowings under the (government-guaranteed) general buyer's credit loan agreement were to be repaid with revenues from mining projects managed by Sicomines SARL.
All infrastructure projects supported through the general buyer's credit loan were part of the so-called “Sino-Congolese Programme." One of the subsidiary loans issued as part of the 'Sino-Congolese Programme' was a $10 million loan for the Bukavu Stadium Construction Project. The loan ultimately achieved a disbursement rate of 83% ($8,255,714.55 out of $10,000,000).
The project involves the construction of a 14,633.44 square meter stadium with 10,000 seats that is located in the city of Bukavu in South Kivu Province. Sinohydro is the contractor responsible for project implementation. It was awarded a $10 million contract (ID#ACGT/DG/020/2015) on August 17, 2015.
Construction began on November 28, 2017. The expected project completion date was November 27, 2018. As of 2021, construction of the stadium had reached a 75% completion rate. However, it is not clear if or when this project was completed.
Sino-Congolais des Mines (Sicomines SARL)