Loading…
Loading grant details…
| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Government of Democratic Republic of Congo |
| Country | Democratic Republic of the Congo |
| Start Date | Nov 26, 2019 |
| End Date | Feb 19, 2028 |
| Duration | 3,007 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 58761 |
China Eximbank provides $301 million preferential buyer’s credit for N’djili Airport Terminal Construction Project On November 26, 2019, China Eximbank and the Government of the Democratic Republic of Congo signed a $301,098,000 preferential buyer’s credit (PBC) agreement for the N’djili Airport Terminal Construction Project.
The loan is secured with revenues that are generated by an airport tax (called “GoPass”) and deposited in an escrow account ("compte séquestre").
The borrower is expected to use the proceeds of the PBC to finance approximately 85% of the cost of a $354,680,000 commercial (EPC) contract between Régie des Voies Aériennes de la République Démocratique du Congo) (RVA) and Weihai International Economic & Technical Cooperative Co., Ltd. (WIETEC), which was signed on September 16, 2013.
The cash balance of the escrow account was $6.64 million as of December 31, 2022 and $6.53 million as of December 31. 2023.
The purpose of the project is to construct a new airport terminal — with an area of 40,617 m2 including a ground floor for arrivals — at N'djili International Airport in Kinshasa.
The project also involves the installation of check-in counters, arrival and departure baggage rooms, public areas, shopping centers, a foundation, and a parking lot (with the ability to accommodate 1200 vehicles).
Weihai International Economic & Technical Cooperative (WIETC) was originally identified as the main EPC contractor responsible for implementation.
However, Chengdu Xinghua Engineering Service Co., Ltd (成都兴华工程服务有限公司) was also identified as a contractor involved in implementation (most likely as a subcontractor). A foundation-laying ceremony took place on May 2, 2018.
As of May 2020, the DRC’s Minister of Transport Didier Mazengu Mukanzu reported to Parliament that the project’s technical and topographical studies and feasibility studies were 80% complete. By September 2020, the project design process was complete and implementation was expected to start by the end of 2020.
As of December 2020, all of the necessary materials and equipment were on-site to begin construction but project implementation had stalled due to the fact that the Congolese Government had not met its counterpart funding commitment. China Eximbank was also withholding loan disbursements.
In August 2021, Alphonse Shungu, the Director General of the RVA, reported that the project had only achieved a 9.21% completion rate.
Then, in 2021 and 2021, Qatar Airways Group (QAG) reportedly prepared a major contract for the renovation and management of three strategic airports in the DRC: N'djili International Airport, Ndolo Airport and Lubumbashi Airport. The feasibility studies were entrusted to the Dutch company NACO, which specializes in airport infrastructure.
The two parties, who signed a memorandum of understanding in March 2021, agreed on a public-private partnership (PPP) under which QAG would shoulder the cost of renovating and updating the three airports on its own, in exchange for managing it for an unspecified length of time (perhaps as long as thirty years).
Under these terms, RVA would no longer manage these airports, depriving it of the bulk of its revenues, especially of the highly controversial ‘go-pass’ tax that travelers have to pay.
By September 2022, the Congolese Government was reportedly looking to end its partnership with WIETC for the construction of the new N'djili airport. Then, on June 8, 2023, the Congolese Government terminated its construction contract with WIETC.
The Chinese company responded by notifying the Congolese Government of its intention to pursue dispute resolution through international arbitration at the International Chamber of Commerce. (ICC) in Paris.
It also warned the Congolese Government that, until an arbitral award was issued by the ICC, WIETC would enjoy contractual rights to access and use the project work site.
As of January 2024, the Congolese government entrusted the Turkish company Milvest, a subsidiary of Miller Holdings, to oversee the resumption of the project with an anticipated start date before September 2023. However, the new implementation arrangement was not approved until March 25, 2024. The project is anticipated to be complete within a two year timeline.
Government of Democratic Republic of Congo
Complete our application form to express your interest and we'll guide you through the process.
Apply for This Grant