Loading…
Loading grant details…
| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Government of Kenya |
| Country | Kenya |
| Start Date | Aug 01, 2017 |
| End Date | Oct 13, 2028 |
| Duration | 4,091 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 58707 |
[Suspended] China Eximbank provides $90.2 million buyer’s credit loan for Kamburu-Embu-Kibirigwi-Thika Transmission Line Project On August 1, 2017, China Eximbank and the Government of Kenya signed a $90,286,383.39 buyer’s credit loan (BCL) agreement for the Kamburu-Embu-Kibirigwi-Thika Transmission Line Project.
The loan carries a maturity of 17-years (final maturity date: July 21, 2034). The other borrowing terms of the BCL are unknown.
However, it is known that the proceeds of the BCL were on-lent to a Kenyan state-owned electricity company called the Kenya Electricity Transmission Company Limited (KETRACO).
The ultimate borrower, KETRACO, used the proceeds of the BCL to finance approximately 85% of the total cost of a $118 million commercial contract between a consortium consisting of China North Industrial Corporation (NORINCO, 中国北方工业有限公司) and Shandong Taikai Power Engineering Co. (TKPE, 山东泰开电力建设工程有限公司) and Kenya's Ministry of Energy and Petroleum, which was signed on January 29, 2016 and amended on May 26, 2017, October 18, 2019, and April 30, 2020.
No BCL (loan) disbursements or principal repayments took place between July 1, 2020 and June 30, 2022 (Fiscal Year 2020-2021 and 2021-2022). The loan’s amount outstanding was zero as of June 30, 2021 and zero as of June 30, 2022.
The purpose of the project is to construct (1) a 153 km, 220kV transmission line from Kamburu to Kibirigwi (via Thika and Embu) with bay extension at the Kamburu substation, (2) a 3 km 132 kV transmission line and three 150MVA 220/132kV substations at Embu, Kibirigwi and Thika, and (3) a 132kV LILO substation at Kibirigwi on the Masinga/Kutus transmission line.
NORINCO and TKPE are the EPC contractors responsible for project implementation. An Environmental and Social Impact Assessment (ESIA) was carried out for the project in June 2009.
Then, a November 2018 Sector Report from the Government of Kenya's Treasury Department identified the project as having cumulative expenditures of KES 2.651 billion as of June 30, 2018; it also identified the project as having achieved a 1% completion rate, with a status designation of ‘need[s] budget provision.’ However, by 2021, the project had achieved a 50% completion rate.
Its originally scheduled completion date is December 2022.
Government of Kenya
Complete our application form to express your interest and we'll guide you through the process.
Apply for This Grant