| Funder | China Development Bank (CDB) |
|---|---|
| Recipient Organization | Government of Ecuador |
| Country | Ecuador |
| Start Date | Jan 01, 2011 |
| End Date | Nov 06, 2031 |
| Duration | 7,614 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 58593 |
CDB loans $41.6 million for Mazar-Dudas Hydroelectric Plant In 2011, the China Development Bank signed a 41.6 million USD loan agreement with the Ecuadorian government to construct the Mazar-Dudas Hydroelectric plant.
According to a Boston University publication and “Resource-Backed Loans: Pitfalls and Potential”, this project was funded through a 2011 China Development Bank loan of $2,052,360,403.03 (Record ID#35950), specifically through the $1.4 billion discretionary component (Tranche A; Record ID#69319).
While the estimated original costs were 50 million USD, the estimated final costs were 83 million USD. The China National Electric Engineering Co. (CNEEC) implemented the project, and it was completed on April 30, 2015.
This project is funded through Tranche A of the 2011 $2 billion CDB loan (Project ID#69319). To ensure we are not double-counting Chinese OF, the transaction amount field is left empty. The amount is captured in Project ID#69319.