China Eximbank provides RMB 594 million government concessional loan for Phase 2 of the 9 Cities Water Supply Project (Linked to Record ID#30903)

¥594K RMB

Funder Export-Import Bank of China (China Eximbank)
Recipient Organization Cameroon Ministry of Economy, Planning, and Regional Development (MINEPAT)
Country Cameroon
Start Date Mar 22, 2018
End Date Jan 31, 2028
Duration 3,602 days
Number of Grantees 1
Roles Recipient
Data Source AidData Chinese Aid
Grant ID 58421
Grant Description

China Eximbank provides RMB 594 million government concessional loan for Phase 2 of the 9 Cities Water Supply Project On March 22, 2018, China Eximbank signed an RMB 594 million (CFA 48.8 billion) government concessional loan (GCL) agreement with Cameroon's Ministry of Economy, Planning and Regional Development for Phase 2 of the 9 Cities Water Supply Project.

📋 Loan / Grant Terms
📅 Maturity20 years
⏳ Grace Period5 years
💹 Interest Rate2%

As of December 31, 2020, the loan (GCL) had achieved a 0% disbursement rate (with an undisbursed balance of CFA 48.8 billion).

The purpose of the second phase of the project is to extend and upgrade drinking water production plants in 9 cities of Sangmélima, Yabassi, Maroua, Garoua, Garoua-Boulai, Bafoussam, Dschang, Bamenda, and Kribi.

Phase 2 is itself scheduled to be undertaken in two parts or phases, the first of which will focus on the cities of Bafoussam, Bamenda, Kribi and Sangmélima (with a goal of providing additional daily water production of 10,000 m3 per city in Bafoussam and Bamenda, and 7,000 m3 per city in Kribi and Sangmélima, for a total of 34,000 m3).

CGCOC Group Co., Ltd is the contractor responsible for Phase 2 implementation.

As of late 2021, all project activities in the cities of Bafoussam, Kribi and Sangmélima were completed and provisionally accepted; however, project activities in Bamenda were on ‘standby’ due to the security situation.

Phase 2 of the 9 Cities Water Supply Project was launched on on August 28, 2023, in Garoua-Boulaï, Lom-et-Djérem department, East Region.

There are some indications that the China Eximbank loan for Phase 2 of the 9 Cities Water Supply Project may have financially underperformed vis-a-vis the original expectations of the lender. In January 2019, Cameroon unilaterally withheld debt service payments to China Eximbank. The lender responded by withholding new loan disbursements.

Then, in July 2019, China Eximbank and the Government of Cameroon signed a debt rescheduling agreement (as captured via Record ID#88213).

Under the terms of the agreement, China Eximbank agreed to reschedule 18 loans previously contracted by the Government of Cameroon — with scheduled principal repayments between July 2019 and March 2022 — by allowing the borrower to defer scheduled principal repayments between July 2019 and March 2022 to later dates but without any maturity extensions.

The total amount of restructured debt was equivalent CFA 148 billion ($253 million) — or 70% of the loan principal that was scheduled for repayment between July 2019 and March 2022.

Under the terms of the agreement, the Government of Cameroon agreed to repay 30% of the loan principal according to the original July 2019-March 2022 schedule (i.e. without any payment deferrals).

The lender and the borrower also agreed to cancel the committed but undisbursed loan balances worth approximately CFA 10 billion (for certain loans with disbursement deadlines that had already passed).

Then, in January 2020, the International Monetary Fund (IMF) classified the Government Cameroon as facing a high risk of debt distress.

Eighteen months later, during an address before Cameroon’s National Assembly on June 28, 2021, the Minister of Water and Energy (MINEE) Gaston Eloundou Esommba provided an update on the ICBC-financed Bini à Warak Hydroelectric Power Plant Project.

He noted that the project had been 'on hold' since November 2019 because ICBC suspended the loan agreement, even though the Government of Cameroon had already mobilized XAF 22 billion of counterpart funding.

He also explained that 'the reason for this suspension is that Cameroon did not settle some of its debts towards China on time, so, it is in a cross-default situation.’

📋 Staff Comments
  1. The Chinese name of this project is 九城市供水项目. The French project title is Projet d’alimentation en eau potable de neuf villes phase II: Dschang, Garoua-boulai, Garoua, Maroua et Yabassi or PROJET D'ALIMENTATION EN EAU POTABLE 09 VILLES PHASE 2.
  2. The project identification number for this transaction in Cameroon's Development Assistance Database (DAD) is CAM/001074.
  3. CGCOC Group Co., Ltd was formerly known as CGC Overseas Construction Group Co., Ltd.
  4. AidData relies on the borrowing terms of the loan that are recorded in a March 2021 publication of the Government of Cameroon’s Caisse Autonome d'Amortissements (CAA).
  5. The loan identification number in the Government of Cameroon's Commonwealth Secretariat Debt Recording and Management System (CS-DRMS) is 2018105.
  6. China Eximbank also financed the first phase of this project (as captured via Project ID#30903). Phase 1 commenced on October 1, 2013 and concluded in August 2017.
📚 Sources & References
  • 中国和喀麦隆签署3项合作协议
  • 中国喀麦隆签署3份协议 总金额超过9亿人民币
  • 中国和喀麦隆签署3项合作协议
  • China signs 973 million RMB-worth cooperation deals with Cameroon
  • Cameroon gets 50bn FCFA Eximbank loan for water supply
  • GOVERNMENT’S ECONOMIC
  • FINANCIAL
  • SOCIAL AND CULTURAL PROGRAMME FOR THE 2020 FINANCIAL YEAR
  • Finance Bill for the 2020 Financial Year
  • The signing of the second phase framework agreement
  • Cameroon Nine Cities Water Supply Project
  • THIRD REVIEW UNDER THE EXTENDED CREDIT FACILITY ARRANGEMENT AND REQUESTS FOR A WAIVER OF NONOBSERVANCE OF A PERFORMANCE CRITERION AND MODIFICATION OF PERFORMANCE CRITERIA—PRESS RELEASE; STAFF REPORT; AND STATEMENT BY THE EXECUTIVE DIRECTOR FOR CAMEROON
  • PROJET D'ALIMENTATION EN EAU POTABLE 09 VILLES PHASE 2
  • State visit of the President of the Republic of Cameroon H. E. Paul BIYA to China
  • Farewell Reception To Chinese Ambassador
  • Chinese Loans to Africa Database
  • SAIS-CARI Loans China
  • DOCUMENT DE STRATÉGIE D’ENDETTEMENT PUBLIC ET DE GESTION DE LA DETTE PUBLIQUE 2019
  • DRS Official Commitments from China through 2020
  • 喀麦隆九城市供水项目
  • 喀麦隆九城市供水项目
  • The minister of Water and Energy before the committee on Finance and the Budget of the national assembly
  • Chinese firm helps bring Cameroon port city with stable clean tap water
  • The 2nd phase of the drinking water supply project launched in the East
  • Government of Cameroon 2020 Register of Chinese Loans and Borrowing Terms Loan applications and disbursements are still being received and processed as the projects continue to evolve. Ongoing monitoring and evaluation are in place to ensure project continuity.
All Grantees

Cameroon Ministry of Economy, Planning, and Regional Development (MINEPAT)

Advertisement
Discover thousands of grant opportunities
Advertisement
Browse Grants on GrantFunds
Interested in applying for this grant?

Complete our application form to express your interest and we'll guide you through the process.

Apply for This Grant