Loading…
Loading grant details…
| Funder | Industrial and Commercial Bank of China (ICBC) |
|---|---|
| Recipient Organization | Zambia Electricity Supply Corp. (ZESCO) |
| Country | Zambia |
| Start Date | Aug 10, 2017 |
| End Date | Jul 25, 2028 |
| Duration | 4,002 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 57573 |
ICBC provides $36.84 million loan to ZESCO Limited for Connection of Lundazi and Chama to National Grid Project On August 10, 2017, the Industrial and Commercial Bank of China (ICBC) signed a $36.84 million loan facility agreement with ZESCO Limited — Zambia’s state-owned power company — for the Chipata-Lundazi-Chama 132KV Transmission Line Project.
The proceeds of the loan were to be used by the borrower to partially finance a commercial contract between ZESCO Limited, Jiangsu Etern Co. and Sinohydro Corporation Ltd., which was signed on or around October 2014. As of December 31, 2017, the loan's amount outstanding was $7.4 million.
The purpose of this 2-part project was to connect Lundazi and Chama districts to the Zambian national power grid because residents were receiving unreliable power from ESCOM Malawi.
It involved the construction of a 305 km, 132 kv transmission line from the Chipata sub-station to Chama via Mwansephangwe, Lundazi, Eggichickeni (Chief Magodis area) as well as four new 33kv substations in Mwasemphangwe, Lundazi, Egichikeni and Chama. Jiangsu Etern Co. and Sinohydro Corporation Ltd were the EPC contractors responsible for project implementation.
The first down payments to the two contractors were made in 2016, thus enabling the preliminary design works to commence.
According to the ZESCO's 2017 Integrated Report (source ID 114272 p. 62), Sinohydro Corporation Ltd mobilized to the site and commenced works during 2017.
However, Jiangsu Etern was still awaiting issuance of a Government of Zambia sovereign guarantee to achieve financial close. It expected to mobilize in the first quarter of 2018. Both projects were scheduled to last 18 months. By the end of 2018, the project had achieved a 40% completion rate. One of the transmissions lines was connected to grid on December 16, 2019.
The project as a whole was completed on or around February 21, 2021.
Zambia Electricity Supply Corp. (ZESCO)
Complete our application form to express your interest and we'll guide you through the process.
Apply for This Grant