Chinese Government provides RMB 40 million interest-free loan for Presidential Palace Expansion Project In November 2010, the Chinese Government and the Government of Burundi signed an agreement that committed funding for a Presidential Palace Expansion Project.
The Presidential Palace (Palais Présidentiel Ntare Rushatsi) is located in Gasenyi, which is 8 km northeast of Bujumbura's city center in Mutimbuzi district.
This project involved the construction of a presidential office building, security guard houses, and sewage treatment facilities in a 10,000 square meters (107,600 sq ft) area. It also involved the installation of equipment.
The Chinese Government reportedly provided RMB 40 million for the implementation of this project, and it was funded with the proceeds from an RMB 50 million interest-free loan agreement that the Chinese Government and the Government of Burundi signed on August 21, 2009 (see Record ID#12303).
China First Highway Engineering Group Co., Ltd. and Hunan Construction Engineering Group were the contractors responsible for implementation. An official groundbreaking ceremony took place on December 21, 2015. However, construction did not begin until March 4, 2016. This project was ultimately completed and handed over to the authorities on February 14, 2019.
The total reported cost of this project is RMB 147 million, but it is unclear if the remaining RMB 107 million came from a Chinese Government grant or interest-free loan.