In 2016, the Chinese Government pledged to help the Government of Uruguay finance the Casavalle School Construction Project.
Then, on October 18, 2016, the two governments signed letters of exchange regarding the Casavalle School Construction Project.
The Chinese Government agreed to provide RMB 14,570,000 (~$2.368 million) of grant funding to support the implementation of the project.
These funds were drawn from an August 2010 Economic and Technical Cooperation Agreement (ETCA) (captured via Record ID#68916) and a June 2011 ETCA (captured via Record ID#41189 and #41190).
Then, on November 29, 2017, the Deputy Secretary of the Presidency of the Republic and President of the Uruguayan Agency for International Cooperation (Agencia Uruguaya de Cooperación International or AUCI), Juan Andrés Roballo, and the Economic and Commercial Counselor of the Embassy of the People's Republic of China in Uruguay, Zhou Quan, signed a project implementation agreement.
The purpose of the project was to construct a public elementary school in the Barrio Borro of Casavalle, a locality of Montevideo.
China Railway 17th Bureau Group Co., Ltd. and Tianli (Beijing) Project Management & Consulting Co., Ltd. were the contractors responsible for project implementation.
Uruguay's National Administration for Public Education (Administración Nacional de Educación Pública, ANEP) was the Uruguayan government agency responsible for the organization, coordination and administration of implementation.
Construction began on November 1, 2018 and the construction period was originally expected to last for one year (estimated project completion date: November 1, 2019). It was ultimately completed and opened for use on February 11, 2020. A provisional project completion (delivery) certificate was issued on February 26, 2020.
On September 29, 2022, the school was officially inaugurated with an event originally postponed due to COVID-19.
The new school has a capacity of 300 students, 12 educational spaces (nine classrooms and three workshops), offices for teachers and administration, a cafeteria for 300 people and that also served as a multifunctional room, reading rooms, sports field, toilets, and warehouses in a space of more than 1,700 m2.
Construction also included paths and public accesses and reforestation outside.
This educational center was planned to be added to the School No. 319 (Escuela Nº 319) that operates in the neighborhood, which has an enrollment of seven hundred students. It is now known as the ‘People's Republic of China’ School.