Completed Development AidData Chinese Aid

China Eximbank provides RMB 1.2 billion government concessional loan for Lahore Orange Line Metro Train Project (Linked to Record ID#53820, #57673, #37280)

¥1.2M RMB

Funder Export-Import Bank of China (China Eximbank)
Recipient Organization Government of Pakistan
Country Pakistan
Start Date Dec 21, 2015
End Date Jan 27, 2030
Duration 5,151 days
Number of Grantees 1
Roles Recipient
Data Source AidData Chinese Aid
Grant ID 54420
Grant Description

China Eximbank provides RMB 1.2 billion government concessional loan for Lahore Orange Line Metro Train Project On April 27, 2011, the Government of Pakistan first announced its interest in pursuing a project to develop a city-wide train system in the eastern city of Lahore.

Lahore, the capital of Punjab province, is Pakistan’s most populous and prosperous province with more than 5 million people.

Pakistani officials expected the new transport system, the first of its kind in the country, to substantially decrease road traffic.

Then, on December 21, 2015, China Eximbank and the Government of Pakistan signed three separate loan agreements for the Lahore Orange Line Metro Train Project. The first loan agreement is a $203.25 million buyer’s credit loan (BCL) agreement [ID#BC-OLL-2015 and ID#2015212493].

📋 Loan / Grant Terms
📅 Maturity20 years
⏳ Grace Period2 years
💹 Interest Rate5.2%

The second loan agreement is a $1,235,480,000 preferential buyer’s credit (PBC) agreement [CHINA EXIMBANK PBC NO. (2015) 34 TOTAL NO. (377) or ID#PBC-OLL15-34377].

📋 Loan / Grant Terms
📅 Maturity20 years
💹 Interest Rate2%

The third loan agreement is an RMB 1,200,000,000 government concessional loan (GCL) loan agreement [ID#GCL-OLL15-20559 or CHINA EXIMBANK GCL NO. (2015) 20 TOTAL NO. (559)].

📋 Loan / Grant Terms
📅 Maturity20 years
💹 Interest Rate2%

The proceeds of the GCL, PBC, and BCL were used by the borrower to finance a commercial contract between Punjab Mass Transit Authority (PMA) and CR-NORINCO [a joint venture of China State Railway Group Co. Ltd. (CR) and China North Industries Corporation (NORINCO)], which was signed on April 20, 2015.

According to the Government of Pakistan’s Economic Affairs Division, $672.7 million of the “mixed credit” (GCL, PBC, and BCL) from China Eximbank had been disbursed as of June 30, 2017.

The Lahore Orange Line Metro Train Project involved the construction of a 27 km two-lane metro bus corridor runs through the heart of Lahore along Multan Road, McLeod Road, and GT Road. The Orange Line connects Ali Town and Dera Gujran via 26 stations with a maximum design speed of 80 km per hour.

The project scope also included the operation and maintenance of metro vehicles, power supply, signal and communication systems, track, and all other mechanical and electrical equipment systems.

Upon completion, the Orange Metro Line was expected to have capacity for 30,000 passenger per hour and serve 250,000 passengers per day. CR-NORINCO — a joint venture of China State Railway Group Co. Ltd. (CR) and China North Industries Corporation (NORINCO) — was the entity responsible for project implementation.

Construction began on June 6, 2016 and the project created a large number of job opportunities for the local community, as nearly 7,500 local residents were employed directly for positions in construction, technology, and management.

The project was initially expected to begin by the end of 2014 and last for 27 months (estimated completed date: March 31, 2017). The Orange Line Metro Train conducted its first trial run on on December 10, 2019. The project was ultimately completed on October 8, 2020.

Since its inception, the Orange Line Metro Train has transported more than 50 million passengers with a punctuality rate of 99.99%, and reduced a 2.5-hour commute to 45 minutes. However, it encountered various problems and delays during implementation.

The Lahore Development Authority began marking sites for demolition in August 2015, including government buildings, royal tombs, mosques, schools, and residences. Civil works were then initiated by CN-NORINCO on October 25, 2015.

Popular protests prompted the Lahore high court to suspend work surrounding heritage sites in January 2016 while the court deliberated the issue.

Then, in August 2016, the Lahore high court ruled that the government could not evict people or harm the heritage sites.

The Punjab provincial government challenged the ruling, and in April 2017, the Supreme Court reversed its decision, allowing construction to continue under 31 conditions to limit the disruption and damage of the project. Then, in May 2019, a special audit of the project project was submitted to the federal government.

The audit revealed losses to the national exchequer and alleged irregularities worth billions of rupees.

More specifically, the audit disclosed that no framework agreement existed between the federal and provincial governments and that sub-contractors were granted several contracts without any approval. The audit claimed that a loss of $1,528,000 had been incurred to the national exchequer. It also claimed more than $1.4 million had been spent on the basis of favoritism with regard to project allowance.

There are some indications that the China Eximbank government concessional loan for the Lahore Orange Line Metro Train Project financially underperformed vis-a-vis the original expectations of the lender. On or around July 1, 2020, China Eximbank and the Government of Pakistan signed a debt suspension agreement.

Under the terms of the agreement, the lender agreed to suspend principal and interest payments due between July 1, 2020 and December 31, 2020 under the government concessional loan agreement for the Lahore Orange Line Metro Train Project. Then, on November 19, 2020, China Eximbank and the Government of Pakistan signed another debt suspension agreement [No.

DSSI2021PHASE1-030].

Under the terms of the agreement, the lender agreed to suspend principal and interest payments due between January 1, 2021 and June 30, 2021 under the government concessional loan agreement for the Lahore Orange Line Metro Train Project.

Then, on or around July 1, 2021, China Eximbank and the Government of Pakistan signed another debt suspension agreement.

Under the terms of the agreement, the lender agreed to suspend principal and interest payments due between July 1, 2021 and December 31, 2021 under the government concessional loan agreement for the Lahore Orange Line Metro Train Project. The debt service suspension (rescheduling) from July 2020-December 2020 is captured via Record ID#96254.

The debt service suspension (rescheduling) from January 2021-June 2021 is captured via Record ID#96256. The debt service suspension (rescheduling) from July 2021-December 2021 is captured via Record ID#96253.

📋 Staff Comments
  1. This project is also known as the Lahore Orange Line Metro Train Project. The Chinese project title is 巴基斯坦拉合尔轨道交通“橙线”项目 or 巴基斯坦拉合尔轨道交通橙线项目.
  2. In January 2017, Industrial and Commercial Bank of China (ICBC) also provided a Rs 1.36 billion short-term loan in additional financing for the Orange Line Metro Project in Pakistan (captured via Project ID #57673).
  3. The project was reportedly financed through a EPC+F arrangement. See https://www.chinca.org/upload/file/20230413/6381700144050388943225072.pdf4. The November 2020 debt suspension agreement [No. DSSI2021PHASE1-030] can be accessed in it entirety via https://www.dropbox.com/s/67n1oq44it27kvu/3.%20Debt%20Suspension%20Agreement%20for%20GCL%20Other%20Projects.pdf?dl=0
📚 Sources & References
  • China Eximbank provides RMB 1.2 billion government concessional loan for the Lahore Orange Line Metro Train Project (Linked to Record ID#37280 and #53820).
  • China OKs $1.7bn for intra-Lhr rail
  • Joint Statement between the Islamic Republic of Pakistan and the People's Republic of China on Establishing the All-Weather Strategic Cooperative Partnership
  • Pakistan
  • China sign pact on Lahore Orange Line metro project
  • Rs165bn Lahore metro train project approved
  • Pakistan
  • China sign Lahore metro train agreement
  • Good news on track: Lahore to get Pakistan’s first metro train
  • Development agenda: Lahore metro train gets green signal
  • Pervez Malik looks China financed projects as game-changer
  • Pervez Malik looks China financed projects as game-changer
  • Why the Orange Line Metro Train in Lahore is highly controversial
  • 拉合尔城市轨道交通橙线项目贷款协议签署
  • Orange Line - Lahore
  • Pakistan Ministry of Finance Economic Affairs Division Annual Status Report 2015-16
  • Pakistan Economic Affairs Division Year Book in the fiscal year of 2016/17
  • Pakistan Ministry of Finance Economic Affairs Division Year Book 2015-16
  • YEAR BOOK 2014-15
  • China’s Global Building Spree RunsInto Trouble in Pakistan
  • Metro First Orange Line Metro train to reach Pakistan by end of this month
  • OLMT blame game: 'Do not blame Chinese for your shortcomings'
  • Orange Line Metro Train: Litigation to cost exchequer over Rs10 billion
  • Financing Orange Line – was the solution optimal?
  • 对外投资合作国别(地区)指南 —— 巴基斯坦2018版
  • Exim Bank Of China Releases Another Installment For Lahore Orange Line Metro Train Project
  • Lahore Orange Line Metro Train Project
  • Pre-Qualification Notice Lahore Orange Line Metro Train Project
  • Introduction on CPEC Projects
  • Pakistan's Lahore Rail Transit 'Orange Line' Project
  • 驻巴基斯坦大使姚敬访问拉合尔
  • Montly Bulletin Foreign Economic Assistance March 2020
  • Lahore Orange Line Metro Train Project (From Ali Town to Dera Gujran)
  • Orange Line Metro Train Project
  • Lahore Orange Line Project Special Report on CPEC Projects (Transportation Infrastructure: Part 5)
  • 北方公司拉合尔橙线项目首个车站进行联调联试检验
  • Concessionary loan from China: After Metro bus
  • Lahore could see Metro train
  • 中巴经济走廊拉合尔轨道交通橙线项目建设完成
  • 中巴经济走廊拉合尔轨道交通橙线项目建设完成
  • 中国向巴基斯坦拉合尔轨道交通项目新增4800万美元软贷款
  • 用金融服务讲好“上合故事”——进出口银行创新金融服务推动上海合作组织成员国共同发展
  • 北方国际合作股份有限公司 2017 年年度报告补充更正公告
  • 巴基斯坦拉合尔橙线轨道项目试运行
  • 巴基斯坦媒体集中报道拉合尔橙线项目贷款协议签约
  • Norinco Technical Proposal
  • SECTION - 3 DESCRIPTION OF THE PROJECT
  • OUT OF THE WAY: LAHORE’S ORANGE LINE GIVES THE BLUES TO PROPERTY OWNERS
  • China signs funding agreement for Lahore metro
  • China financing Orange Line Metro Train/ Shahbaz Sharif
  • HERITAGE RELATED DOCUMENTS SUBMITTED TO THE COURTS BY THE GOVT OF THE PUNJAB AND ITS AGENCIES
  • 巴基斯坦媒体集中报道拉合尔橙线项目贷款协议签约
  • Lahore Metro Orange Line Railway First Train was Off Production Line
  • DEBT BULLETIN‐ GOVERNMENT OF THE PUNJAB
  • Repayment of Chinese infrastructure loans to start in 2021
  • Project Brief Of Lahore Orange Line Metro Train
  • Pakistan Estimates of Foreign Assistance 2018-2019
  • Pakistan Economic Survey 2017-2018: Chapter 13 - Transport and Communication
  • Audit of Orange Line project’s civil works complete
  • Corruption worth billions of rupees unearthed in Orange Line Metro Train project, 2022 Best Practices of Sustainable Infrastructure. Projects
  • SPECIALAUDIT REPORT ON CONSTRUCTION OF LAHORE ORANGE LINE METROTRAIN PROJECT Loan applications and disbursements are still being received and processed as the projects continue to evolve. Ongoing monitoring and evaluation are in place to ensure project continuity.
All Grantees

Government of Pakistan

Advertisement
Apply for grants with GrantFunds
Advertisement
Browse Grants on GrantFunds
Interested in applying for this grant?

Complete our application form to express your interest and we'll guide you through the process.

Apply for This Grant