Loading…
Loading grant details…
| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Ministry of Finance of the Kyrgyz Republic |
| Country | Kyrgyz Republic |
| Start Date | Jun 15, 2015 |
| End Date | Nov 05, 2031 |
| Duration | 5,987 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 53585 |
China Eximbank provides $185 million preferential buyer’s credit for Aral-Kazarman Section (195 km-291 km) of the Alternative North-South Road Project On June 15, 2015, China Eximbank and the Government of the Kyrgyz Republic's Ministry of Finance signed a $185,254,119 preferential buyer credit (PBC) loan agreement [CHINA EXIMBANK PBC NO. (2015) 4 TOTAL NO. (346)] for the Aral-Kazarman Section (195 km-291 km) of the Alternative North-South Road Project.
The proceeds of the loan were to be used by the borrower to partially finance a May 4, 2014 commercial contract [EXMB/KG/NS-05] worth $298,796,966.13 between the Ministry of Transport and Communications of the Kyrgyz Republic and China Road and Bridge Corporation (CRBC).
According to internal data that the Kyrgyz Ministry of Finance shared with AidData in July 2022, this loan achieved a disbursement rate of 83.8% ($155,374,422.40 out of $185,254,119) as of December 31, 2021 and its amount outstanding was $155,374,422.40 as of December 31, 2021.
The purpose of the project was to construct a section of the Alternative North-South Road that runs from Aral to Kazarman (195 km to 291 km).
The aim of this international North-South transport corridor is to reduce trade costs and connect Russia, Central Asia, Iran, and India. CRBC was the EPC contractor responsible for project implementation. Construction began on August 10, 2015. However, as of December 2020, the project had still only achieved a 70% completion rate.
The project was ultimately completed on November 10, 2021. It was originally scheduled for completion on April 10, 2020. This project has also been plagued by controversy.
According to a 2018 investigation, former Minister of Transport and Communications Kalykbek Sultanov and the Minister of Transport and Communications at the time (Zhamshitbek Kalilov) may have colluded with the contractor responsible for project implementation (CRBC) to embezzle funds that were allocated for the Alternative North-South Road by China Eximbank.
The investigation found the project input costs were inflated by several orders of magnitude — from paying $1.1 per kilogram of cement (while the cost on the local market was $0.07) to paying $2,000 a month to provide office space to an engineer on the construction site.
Ministry of Finance of the Kyrgyz Republic
Complete our application form to express your interest and we'll guide you through the process.
Apply for This Grant