Loading…

Loading grant details…

Active Development AidData Chinese Aid

China Eximbank provides RMB 1.636 billion government concessional loan for Kandy North Pathadumbara Integrated Water Supply Project

¥1.64M RMB

Funder Export-Import Bank of China (China Eximbank)
Recipient Organization Sri Lanka Ministry of Finance
Country Sri Lanka
Start Date Dec 22, 2017
End Date Aug 28, 2029
Duration 4,267 days
Number of Grantees 1
Roles Recipient
Data Source AidData Chinese Aid
Grant ID 53528
Grant Description

China Eximbank provides RMB 1.636 billion government concessional loan for Kandy North Pathadumbara Integrated Water Supply Project On May 16, 2017, the Chinese Government and the Government of Sri Lanka signed a preferential loan framework agreement for the Kandy North Pathadumbara Integrated Water Supply Project.

Then, on December 22, 2017, China Eximbank and the Government of Sri Lanka's Ministry of Finance and Mass Media signed an RMB 1,636,553,500 government concessional loan (GCL) agreement [CHINA EXIMBANK GCL NO. (2017) 07 TOTAL NO. (612)] for the Kandy North Pathadumbara Integrated Water Supply Project (KNPIWSP).

📋 Loan / Grant Terms
⏳ Grace Period6 years

The loan went into effect on May 29, 2018.

Sri Lanka's Ministry of Finance and Mass Media on-lent the proceeds of the loan to Sri Lanka’s National Water Supply and Drainage Board.

The borrower was expected to use the loan proceeds to finance a $254,518,429.03 commercial contract (ID# P&P/DB/PATHADUMBARA/2013) between Sri Lanka’s National Water Supply and Drainage Board and Sinohydro Corporation Limited, which was signed on June 16, 2015.

China Eximbank disbursed an unknown amount in 2017 and 2018, RMB 274,817,342.53 in 2019, RMB 349,089,845 in 2020, RMB 346,713,167 in 2021, and RMB 50,798,397.47 in 2022. The loan had achieved a 62.4% disbursement rate (RMB 1,021,418,752 out of RMB 1,636,553,500) as of September 2022. The borrower made no repayments between 2017 and 2021.

The loan's amount outstanding was RMB 349,089,845 as of December 31, 2020, RMB 695,803,012 as of December 31, 2021, and RMB 746,601,410 as of June 30, 2022.

The objective of the project is to provide a safe pipe-borne water supply facility to six divisions, namely Pathadumbara, Harispattuwa, Akurana, Pujapitiya, Kandy Four Gravets, and Thumpane.

The scope of the project includes the construction of a clear water reservoir (2100m3 within the existing water treatment plant), a filtration unit, a flocculation unit, a new pump station, and improvements to existing stations, sludge lagoon, service reservoirs, and pump houses.

The project also includes the improvement of existing pump stations and the supply and laying of distribution lines and transmission lines. The project is distributed in 6 administrative areas in the north of Kandy. The construction area is about 318 square kilometers.

The main construction content is the laying of 83 kilometers of water supply pipelines, 567 kilometers of water distribution pipelines, 29 pools, and 18 pumping stations. After all the planning of the project is completed, it is expected to meet the domestic water demand of 470,000 people. PowerChina is the contractor responsible for project implementation.

As of September 30, 2018, the project had achieved a ‘physical progress’ rate of 4%.

The loan agreement had already been finalized at that time, but cabinet approval was needed for deviations in the project scope. Land acquisition and procurement activities were underway. As of December 31, 2018, the project had achieved a 'physical progress rate' of 7.42%. Then, on September 21, 2019, a groundbreaking ceremony took place.

As of June 30, 2022, the project had achieved a ‘physical progress’ rate of 79.1%. The project was originally expected to reach completion in August 2022.

📋 Staff Comments
  1. This project is also known as the Kandy North Pathadumbara Integrated WSP. The Chinese project title is 提北部帕特杜玛巴若综合供水工程项.
  2. The Government of Sri Lanka loan key number is 2017041.
  3. Some official sources suggest that the loan disbursed RMB 74,272,502.44 in 2020 and RMB 264,311,211.33 in 2021. This issue warrants further investigation.
  4. The China Eximbank loan agreement can be accessed in its entirety via https://www.dropbox.com/s/a778ddcjkcqr2lm/Sri%20Lanka%202017%20China%20Eximbank%20GCL%20for%20Kandy%20North%20Pathadumbara%20Integratd%20Water%20Supply%20Project.pdf?dl=0.
📚 Sources & References
  • China Enterprise Sri Lanka Kangti North Integrated Water Supply Project starts
  • Commencement of the Pattuma Baro Integrated Water Supply Project in Kandy
  • Sri Lanka
  • Government Concessional Loan: On Kandy North-Pathadumbara Integrated Water Supply Project
  • Kandy North-Pathadumbara Integrated Water Supply Project
  • Kandy-North Pathadumbara Integrated Water Supply Project
  • Performance Report 2017
  • Progress of development projects and programmes as at 31st March 2018
  • Progress of development projects and programmes being implemented in 2017 ( as at 31st December 2017)
  • Progress of Large and Mega Scale Development Projects Second Quarter - Year 2021
  • Resource Mobilization
  • Sri Lanka PM attends inaugurating ceremony of POWERCHINA project
  • Three Concessional Loans of USD 492 mn from the EXIM bank of China for Infrastructure Development of Sri Lanka
  • Treasury Funded Water Supply Projects
  • 中企承建斯里兰卡最大供水项目开工
  • 中企承建的斯里兰卡康提北综合供水项目开工
  • 中企承建的斯里兰卡康提北综合供水项目开工
  • 中企承建的斯里兰卡康提北综合供水项目开工
  • 斯里兰卡总理出席中国电建承建的康提供水项目开工仪式
  • 驻斯里兰卡大使程学源与斯总理维克拉马辛哈共同参加康提北供水项目开工仪式
  • 驻斯里兰卡大使程学源与斯总理维克拉马辛哈共同参加康提北供水项目开工仪式
  • 驻斯里兰卡大使程学源与斯总理维克拉马辛哈共同参加康提北供水项目开工仪式 Loan applications and disbursements are still being received and processed as the projects continue to evolve. Ongoing monitoring and evaluation are in place to ensure project continuity.
All Grantees

Sri Lanka Ministry of Finance

Advertisement
Apply for grants with GrantFunds
Advertisement
Browse Grants on GrantFunds
Interested in applying for this grant?

Complete our application form to express your interest and we'll guide you through the process.

Apply for This Grant