In 2009, the Chinese Government provided a $14,880,995.97 grant to the Government of the Democratic Republic of Congo for the 23 km Bukavu Airport Road Rehabilitation Project.
This project involved the rehabilitation of Bukavu Airport Road in South Kivu (measuring 22.746 kilometers in length), which runs from Bukavu to the Kavumu airport. China Road and Bridge Corporation was the contractor responsible for implementation of the project. Construction began on August 26, 2009.
The planned construction period was 24 months, but construction was completed in 16 months, on December 18, 2010. According to the Aid Management Platform, $14,875,549.05 was ultimately disbursed in support of this project.