Loading…

Loading grant details…

Completed Mixed AidData Chinese Aid

China Eximbank contributes $229,509,300 USD million to syndicated buyer’s credit loan for EETC 500KV Transmission Lines Project (Linked to Record ID#98763 and #58351)

$229.51M USD

Funder Export-Import Bank of China (China Eximbank)
Recipient Organization Egypt Electricity Transmission Company
Country Egypt
Start Date May 15, 2017
End Date Nov 06, 2028
Duration 4,193 days
Number of Grantees 1
Roles Recipient
Data Source AidData Chinese Aid
Grant ID 53069
Grant Description

In 2017, Chinese banks contribute to USD 690,018,600 million to syndicated buyer’s credit loan for EETC 500KV Transmission Lines Project, Egypt On January 21, 2016, the President of Egypt, Abdel Fattah El Sisi, and the President of China, Xi Jingping signed an Economic and Technical Cooperation Agreement (ETCA) in which the parties agreed to upgrade the capabilities of Egypt’s national 500kV backbone power grid.

Then, on May 15, 2017, during a Belt and Road Forum in Beijing, the Egyptian Electricity Transmission Company (EETC) signed a $690,018,600 syndicated buyer’s credit loan agreement with three Chinese state-owned banks — the Export-Import Bank of China (China Eximbank), which served as the lead arranger, China Development Bank (CDB), and the Beijing Branch of Bank of China (BOC) — for the EETC 500KV Transmission Lines Project.

China Development Bank contributed $231,000,000 to the loan syndicate (captured in Record ID#58351). China Eximbank and Bank of China contributed the remaining $459,018,600. AidData assumes that both members contributed equally ($229,509,300) (captured in Record ID#53069 and #98763). The loan carried a 15-year maturity.

Its interest rate and grace period are unknown. Sinosure provided long-term buyer’s credit insurance to the borrower. Egypt’s Ministry of Finance also issued a sovereign guarantee in support of the loan in June 2017.

The proceeds of the syndicated loan were to be used by the borrower to finance 85% of the total cost ($811,790,000) of an engineering, procurement and construction (EPC) contract that EETC signed with State Grid Corporation of China (SGCC) on January 21, 2016. EETC assumed responsibility for the remaining 15% through an advance payment to SGCC.

This project involved the construction of 1,210 km of high voltage (500 kV double-circuit AC) overhead transmission lines in the northern, central and southern parts of the Nile River Delta region. The lines were mainly distributed in areas near gas-fired power stations in the east of the Nile River Delta region.

The project was implemented in two phases and divided into 15 segments (or ‘lots’).

It was envisaged that the project would increase the supply of reliable power to the Nile River Delta region, promote upstream and downstream industries in Egypt, and create 7,000 new jobs.

China Electric Power Equipment and Technology Co., Ltd. (CET) — a subsidiary of SGCC — was the general contractor responsible for the implementation.

However, it hired several subcontractors, including China Energy Engineering Corporation (CEEC), Hubei Engineering Co., Ltd., and Power Construction Corporation of China (PowerChina).

It also hired Jiangsu Zhongtian Technologies Software Technology Co., Ltd, a private Chinese company, for all line equipment and electric metal fittings. The project officially commenced on May 6, 2016.

Then, on November 3, 2016, 3 transmission lines with a total length of 380 km (part of Phase 1) were successfully put into operation. In May 2017, the construction of an additional transmission line was completed. On September 4, 2017, an agreement on Phase 2 was signed during the BRICS summit.

The same month witnessed the completion of a 94 km section that began in April 2016 and was undertaken by Hubei Engineering Co., Ltd. By the end of 2017, the borrower had drawn $115,000,000 from CDB’s contribution to the syndicated loan.

However, the size of the borrower’s drawdowns from the Bank of China’s contribution and China Eximbank’s contribution are unknown. Another 80 km segment was completed on November 26, 2018.

Two additional transmission lines — an 80 km line from Samanoud to Banha and a 94 km line from Borosus to Samanoud — were completed by Hubei Engineering Co., Ltd. in January 2019. As of mid-2019, the project had achieved a 96% completion rate. By the end of June 2019, another 194 km of lines were constructed and the project reached full completion.

📋 Staff Comments
  1. This project is also known as the EETC 500 KV Transmission Project, the Upgrade Project of EETC 500 kV National Backbone Grid, the Egyptian EETC 500 kV Backbone Network Upgrading and Transforming Transmission Project, and the 500 KV Electric Power Transmission Lines Project, and the EETC 500KV Transmission Lines Project (Phase I and Phase I).
  2. The Chinese project title is 国家电网500千伏输电线路工程项目 and 埃及500kV输电线路项目.
  3. In the database of Chinese loan commitments that SAIS-CARI published in July 2020 and the Overseas Development Finance Dataset that Boston University’s Global Development Policy Center published in December 2020, China Eximbank is identified as the only lender that financed this project. However, multiple official sources identify this project as being financed by three Chinese banks — China Development Bank, Bank of China, and China Eximbank — through a syndicated loan.
  4. This project achieved financial close on October 10, 2017. However, it is not clear how the agreement that was signed on October 10, 2017 is different from the agreement that was signed on May 15, 2017. This issue merits further investigation.
  5. At least one source (https://amritec.com/energy/) indicates that this project was financed according to an EPC+F model. This issue warrants further investigation.
  6. The exact size of Bank of China and China Eximbank's respective financial contributions to the $459 million syndicated loan are unknown. For the time being, AidData assumes that both of the lending syndicate contributed equal amounts ($229,509,300).
📚 Sources & References
  • China’s Global Energy Finance: Chinese Development Bank (CDB) and Export-Import Bank of China (Ex-Im) 2018
  • EETC Transmission Network (1210KM) China Exim Facility, وزير المالية:ضمانات مالية بقيمة 29ر1 مليار دولار لهيئة البترول وشركتي وسط الدلتا والمصرية لنقل الكهرباء, “中国设计”成就埃及史上最大电网升级改造
  • 中国电建承建埃及规模最大输电线路投产送电, 【建设公司】签订埃及EETC 500kV输电线路一期第二段工程合同
  • State Grid to complete construction of electric lines along 800 kms next month
  • 江苏中天科技股份有限公司关于重大项目中标情况的公告
  • Egypt inks $250m transport deal with China’s State Grid
  • EETC 500KV Transmission Lines Project
  • Egypt's largest power transmission project begins operating
  • 进出口银行牵头支持中埃产能合作
  • EETC signs for $757 loan with Export-Import Bank of China
  • THE ARAB REPUBLIC OF EGYPT U.S.$30,000,000,000 Global Medium Term Note Programme
  • CET_ Making Electrical Waves On the Nile _ HSBC China
  • Chinese company completes two power transmission lines in Egypt - Xinhua Silk Road
  • China Electric Power Equipment and Technology Co.
  • Ltd Company Profile
  • The firsts achieved under Belt and Road Initiative[5]- Chinadaily.com.cn
  • 国家电网
  • Egyptian EETC 500 kV Backbone Network Upgrading and Transforming Transmission Project launched
  • Egypt’s largest power transmission project completes
  • Finance min. approves dlrs 1.29 bn financial guarantees for petroleum, electricity firms-SIS
  • 中非民间商会赴埃及考察总结 - 中非民间商会官方网站
  • T 年度报告 国家开发银行 2017 年度报告CHINA DEVELOPMENT BANK ANNUAL REPORT 2017
  • 项目掠影_埃及500kV输电线路项目, 【特别策划】国开行 用优质服务护航“一带一路”_中国金融家_中国金融新闻网, 2017年中埃合作概况
  • Project Shows_500 KV Electric Power Transmission Lines Project in Egypt
  • 埃及500kV输电线路项目
  • EETC 500KV Transmission Lines Project
  • EETC 500kV Transmission Lines Project for Upgrading National Grid of Egypt
  • Abolilac - Projects, 【建设公司】埃及Borolus线路进入全面架线施工阶段, 【建设公司】埃及EETC项目banha线路正式开工
  • 中电装备公司总承包建设的埃及最大输电线路工程正式开工
  • Chinese Loans to Africa Database
  • China's Overseas Development Finance
  • 进出口银行的非洲足迹—埃及篇 Loan applications and disbursements are still being received and processed as the projects continue to evolve. Ongoing monitoring and evaluation are in place to ensure project continuity.
All Grantees

Egypt Electricity Transmission Company

Advertisement
Discover thousands of grant opportunities
Advertisement
Browse Grants on GrantFunds
Interested in applying for this grant?

Complete our application form to express your interest and we'll guide you through the process.

Apply for This Grant