| Funder | China Development Bank (CDB) |
|---|---|
| Recipient Organization | Electricity Supply Organization (Eskom) |
| Country | South Africa |
| Start Date | Oct 03, 2016 |
| End Date | Jul 21, 2033 |
| Duration | 6,135 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 52560 |
China Development Bank provides $500 million loan to Eskom for Medupi, Kusile, and Ingula Power Plants On October 3, 2016, China Development Bank and the Electricity Supply Commission (Eskom) — South Africa's state-owned electric power company — signed a $500 million loan agreement. The South African government-guaranteed loan was payable three years after the date the loan agreement was signed.
Its interest rate is unknown.
The proceeds of the loan were intended to support Eskom’s capital expansion program, including the Medupi, Kusile, and Ingula power plants and the Matla mine 1 shaft relocation. The loan fully disbursed in December 2016.
Medupi is a coal-fired power plant with a capacity of 4764MW, Kusile is a coal-fired power plant with a capacity of 4800MW, and Ingula is a pumped-storage hydroelectric power plant with a capacity of 1332MW. As of 2018, the Ingula Plant was fully operational, but the Medupi and Kusile Plants were still under construction.
1. In 2017, CDB provided an additional $1.5 billion loan to Eskom for the Medupi Power Plant, which is captured via Record ID#58385.
Electricity Supply Organization (Eskom)
Complete our application form to express your interest and we'll guide you through the process.
Apply for This Grant