| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Government of Guinea |
| Country | Guinea |
| Start Date | Jan 01, 2014 |
| End Date | May 13, 2026 |
| Duration | 4,515 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 52224 |
China Eximbank provides $214 million preferential buyer’s credit for Fiber Optic Cable Network Project In 2014, the Export-Import Bank of China and the Government of Guinea signed a $214.2 million preferential buyer’s credit (PBC) loan for the Fiber Optic Cable Network Project. The PBC financed 90% of the $238 million total cost of the project.
The Government of Guinea used the proceeds from the PBC to on-lend to a project company and special purpose vehicle (SPV) called Société de Gestion et d'Exploitation du Backbone National (SOGEB).
The loan's principal amount outstanding was $172.09 million as of March 31, 2020, $172.09 million as of June 30, 2020, $214 million as of December 31, 2020, $214 million as of June 30, 2022, and $214 million as of September 30, 2022.
The project involved the construction of a 4352 km fiber optic cable network as well as data centers and network monitoring centers.
The fiber optic cable network consisted of 14 major sections: Kankan-Nzérékoré, Kankan-Mandiana, Kouroussa-Siguiri-Kourémalé, Faranah-Kissidougou-Ouamou, Guéckedou-Bofossou-Macenta, Coyah-Forécariah-Farmoreyah, Boké-Gaoual-Koundara, Conakry-Boké, Conakry-Mamou, Mamou-Labé, Mamou-Kankan, Mamou-Faranah, Kolaboui-Kamsar and Tanéné-Fria.
Huawei was the contractor responsible for implementation. A formal project commencement ceremony took place on December 22, 2014. However, construction did not begin until July 25, 2015. This project was completed on or around April 28, 2020.
Government of Guinea
Complete our application form to express your interest and we'll guide you through the process.
Apply for This Grant