| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Government of Kyrgyzstan |
| Country | Kyrgyz Republic |
| Start Date | Oct 15, 2009 |
| End Date | Sep 05, 2031 |
| Duration | 7,995 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 46348 |
China Eximbank provides $200 million preferential buyer’s credit for Section 1 of Bishkek–Naryn–Torugart Road Rehabilitation Project (9km-272km) On October 15, 2009, China Eximbank and the Government of the Kyrgyz Republic signed a preferential buyer’s credit (PBC) agreement [CHINA EXIMBANK PBC NO. 2009 (25) TOTAL NO. (87)] worth $199,999,703 for the Section 1 of Bishkek–Naryn–Torugart Road Rehabilitation Project (from kilometer 9 to kilometer 272).
According to the Government of the Kyrgyz Republic’s Aid Management Platform (AMP), the first loan disbursement (of $189,999,717.85) took place on July 1, 2013 and the second and final loan disbursement (of $10,000,000) took place on December 31, 2014. The same source notes that, as of 2014, had achieved a 100% disbursement rate ($199,999,717.85 out of $199,999,703).
According to internal data that the Kyrgyz Ministry of Finance shared with AidData in July 2022, this loan achieved a disbursement rate of 10% as of December 31, 2021 and its amount outstanding was $114,486,759.69 as of December 31, 2021.
This project sought to upgrade rehabilitate a 223 km stretch along the Bishkek–Naryn–Torugart Road between kilometer 9 to kilometer 272 (9km-272km).
The Bishkek-Naryn-Torugart road is one of the main transport routes within Kyrgyzstan and comprises part of "Europe-East Asia" CAREC Transport Corridor. China Road and Bridge Corporation was the contractor responsible for project implementation. A “notice to commence” was issued to the contractor on May 1, 2010.
Section 1 (from kilometer 9 to km 103) was completed on December 31, 2012.
However, there are some indications that the preferential buyer's credit for the Section 1 of Bishkek–Naryn–Torugart Road Rehabilitation Project (9km-272km) financially underperformed vis-a-vis the original expectations of the lender.
On or around July 1, 2021, China Eximbank and the Government of the Kyrgyz Republic signed a debt suspension agreement [No. DSSI2021PHASE2-029].
Under the terms of the agreement (captured via Record ID#96102), the lender agreed to suspend principal and interest payments due between July 1, 2021 and December 31, 2021 under the preferential buyer's credit agreement for the Section 1 of Bishkek–Naryn–Torugart Road Rehabilitation Project (9km-272km).
Government of Kyrgyzstan