| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Sino-Congolais des Mines (Sicomines SARL) |
| Country | Democratic Republic of the Congo |
| Start Date | Aug 17, 2015 |
| End Date | Aug 04, 2028 |
| Duration | 4,736 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 46235 |
[Sino-Congolese Programme] China Eximbank provides $5 million loan for Phase 1 of Uvira Road Rehabilitation and Modernization Project In 2008, China Eximbank issued a $3.003 billion general buyer's credit loan to Sino–Congolais des Mines (Sicomines SARL) — a joint venture — to finance infrastructure projects in the DRC (as captured via Record ID#450).
All subsidiary borrowings under the (government-guaranteed) general buyer's credit loan agreement were to be repaid with revenues from mining projects managed by Sicomines SARL.
All infrastructure projects supported through the general buyer's credit loan were part of the so-called “Sino-Congolese Programme." One of the subsidiary loans issued as part of the 'Sino-Congolese Programme' was a $5 million loan (issued in 2009) for Phase I of the Uvira Road Rehabilitation and Modernization Project.
The loan ultimately achieved a disbursement rate of 100% ($5 million out of $5 million).
The project involved the rehabilitation and modernization of 5km of highways and roads of the city of Uvira in South Kivu Province. Sinohydro was the contractor responsible for project implementation. It was awarded a $5 million contract (ID#ACGT/DG/019/2015) on August 17, 2015. Construction began on December 1, 2016 and the project was completed on July 16, 2019.
The project’s originally scheduled completion date was April 14, 2018.
Sino-Congolais des Mines (Sicomines SARL)